East Central RailwayIn Progress

Earthwork in embankment, blanketing, construction of minor bridges, RUB, LHS and other allied misc. works between Manolapatti Halt (excl.) to Baghaily (excl.) i.e. from Km 36.00 to KM 44.00 (including Khajuri Bazar as crossing station) in connection with construction of new B.G. rail line between Araria-Supaul.

Estimate Cost

₹112.53 Cr

Sanctioned estimate

Tendered Cost

₹103.61 Cr

-7.9% vs estimate

Physical Progress

20%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹103.61 Cr
Progress20%
Started20-12-2024
Target DOC31-12-2026
Mahboob Alam CE/C/NC/MHX; Sri Pankaj Kumar Dy CE/C/III/SPJ; Sri H R Chaudhary AEN/C/SRGR

Work Details

5 Fields
Work No.
62
Acceptance / LOA
CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-30-23-24/10684730104503
Officer in Charge
Mahboob Alam CE/C/NC/MHX; Sri Pankaj Kumar Dy CE/C/III/SPJ; Sri H R Chaudhary AEN/C/SRGR
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹112.53 Cr
Tendered Cost
₹103.61 Cr
Physical Progress
20%
Date Started
20-12-2024
Original DOC
31-12-2026
Extended DOC
N/A

Earthwork in embankment, blanketing, construction of minor bridges, RUB, LHS and other allied misc. works between Manolapatti Halt (excl.) to Baghaily (excl.) i.e. from Km 36.00 to KM 44.00 (including Khajuri Bazar as crossing station) in connection with construction of new B.G. rail line between Araria-Supaul. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s ARIHANT CONTRACTORS PRIVATE LIMITED-SUPAUL. The tendered cost of the work is ₹103.61 Cr, and it is currently In Progress with physical progress recorded at 20%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work in progress

?

Frequently Asked Questions

QWhat is the current status of the railway work "Earthwork in embankment, blanketing, construction of minor bridges, RUB, LHS and"?
Status: In Progress. This East Central Railway work is being executed by M/s ARIHANT CONTRACTORS PRIVATE LIMITED-SUPAUL. Physical progress stands at 20%. Current date of completion (DOC): 31-12-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s ARIHANT CONTRACTORS PRIVATE LIMITED-SUPAUL. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-30-23-24/10684730104503. Work started on 20-12-2024.
QWhat is the cost of this railway work?
The tendered cost of "Earthwork in embankment, blanketing, construction of minor b" is ₹103.61 Cr (against an estimate of ₹112.53 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Earthwork in embankment, blanketing, construction of minor b" is one of hundreds of railway works covered.