East Central RailwayIn Progress

Earthwork, spreading of second hand PSC sleeper over prepared surface, approach road & misc. work for construction of Rail level wharf as per five line crossing at Harauli Fatehpur in connection with construction of Hajipur-Sagauli new rail line project

Estimate Cost

₹24.51 Cr

Sanctioned estimate

Tendered Cost

₹21.70 Cr

-11.5% vs estimate

Physical Progress

37%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹21.70 Cr
Progress37%
Started03-05-2024
Target DOC31-07-2026
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP

Work Details

5 Fields
Work No.
296
Agency
Hari Swata JV-Begusarai, At P.O.: Bihat, Tola-Khemkaranpur
P.S.: Barauni, Dist.: Begusarai, Bihar-851135, India
Acceptance / LOA
CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-46-23-24 / 10231030102327 dt 03.05.24
Officer in Charge
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹24.51 Cr
Tendered Cost
₹21.70 Cr
Physical Progress
37%
Date Started
03-05-2024
Original DOC
03-04-2025
Extended DOC
31-07-2026

Earthwork, spreading of second hand PSC sleeper over prepared surface, approach road & misc. work for construction of Rail level wharf as per five line crossing at Harauli Fatehpur in connection with construction of Hajipur-Sagauli new rail line project is an East Central Railway (ECR) infrastructure work in Bihar, executed by Hari Swata JV-Begusarai. The tendered cost of the work is ₹21.70 Cr, and it is currently In Progress with physical progress recorded at 37%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Earthwork, spreading of second hand PSC sleeper over prepared surface, approach "?
Status: In Progress. This East Central Railway work is being executed by Hari Swata JV-Begusarai. Physical progress stands at 37%. Current date of completion (DOC): 31-07-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is Hari Swata JV-Begusarai, At P.O.: Bihat, Tola-Khemkaranpur, P.S.: Barauni, Dist.: Begusarai, Bihar-851135, India. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-46-23-24 / 10231030102327 dt 03.05.24. Work started on 03-05-2024.
QWhat is the cost of this railway work?
The tendered cost of "Earthwork, spreading of second hand PSC sleeper over prepare" is ₹21.70 Cr (against an estimate of ₹24.51 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Earthwork, spreading of second hand PSC sleeper over prepare" is one of hundreds of railway works covered.