East Central RailwayOverdue

Left over work for construction of station building, platform, S&T complex, gate lodge & FOB etc. at Harnagar in connection with SKI-HPO new line.

Estimate Cost

₹8.03 Cr

Sanctioned estimate

Tendered Cost

₹8.81 Cr

+9.7% vs estimate

Physical Progress

85%

Work completed

Status

Overdue

Past target DOC

East Central Railway — CAO (Con)Overdue
Tendered₹8.81 Cr
Progress85%
Started17-10-2016
Target DOC31-12-2024
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/I/SPJ; Rakesh Ranjan, AEN/C/SPJ

Work Details

5 Fields
Work No.
170
Agency
Acceptance / LOA
ECR/CAO/C/WT/71/N/0380 Dt 28.09.2016 ** ECR/CAO/Con/WT/Agt/20 dated 30.12.16
Officer in Charge
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/I/SPJ; Rakesh Ranjan, AEN/C/SPJ
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹8.03 Cr
Tendered Cost
₹8.81 Cr
Physical Progress
85%
Date Started
17-10-2016
Original DOC
27-03-2017
Extended DOC
31-12-2024

Left over work for construction of station building, platform, S&T complex, gate lodge & FOB etc. at Harnagar in connection with SKI-HPO new line. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Ganga Construction Co. The tendered cost of the work is ₹8.81 Cr, and it is currently Overdue with physical progress recorded at 85%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Left over work for construction of station building, platform, S&T complex, gate"?
Status: Overdue (overdue). This East Central Railway work is being executed by M/s Ganga Construction Co. Physical progress stands at 85%. Current date of completion (DOC): 31-12-2024.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Ganga Construction Co, Vishwanath Nagar, PO & Distt.-Begusarai.. Acceptance / agreement reference: ECR/CAO/C/WT/71/N/0380 Dt 28.09.2016 ** ECR/CAO/Con/WT/Agt/20 dated 30.12.16. Work started on 17-10-2016.
QWhat is the cost of this railway work?
The tendered cost of "Left over work for construction of station building, platfor" is ₹8.81 Cr (against an estimate of ₹8.03 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Left over work for construction of station building, platfor" is one of hundreds of railway works covered.