Umagaon-Saharsa (Package-V) Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi

UPC: N/09072/01006/BR

Physical Progress

99.5%

Drone-monitored

Financial Progress

100.0%

Of awarded cost

Awarded Cost

₹552 Cr

Contract value

Length

39.183 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

2196

Aerial captures

Project Progress

Physical Progress99.5%
Financial Progress100.0%

Stage

PCC Issued, CC Pending

Due Date

14-12-2025

Likely Date

30-09-2026

Completion

99.5%

Physical Done

DoneRemaining

Project Timeline

Awarded

15-12-2023

Construction Started

15-12-2023

In Progress

Near Completion

13-09-2025

Completed

30-09-2026

Physical vs Financial Progress

Project Details

UPC

N/09072/01006/BR

National Highway

327E

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

39.183 km

Contractor

Dhariwal Buildtech Limited

Project Stage

PCC Issued, CC Pending

Drone Frames

2196 frames

Last Flight

2026-03-23

Cost & Timeline

Awarded Cost

₹551.51 Cr

Capital Cost

₹768.35 Cr

Start Date

15-12-2023

PCOD Date

13-09-2025

Scheduled Completion

14-12-2025

Likely Completion

30-09-2026

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-20 21:37:25

Contractor Profile

Dhariwal Buildtech Limited

RO-Patna327EHAM

Project Intelligence

1

Construction is 99.5% complete — nearing final stages.

2

Project is on schedule or ahead of planned completion date.

3

Covers 39.183 km on 327E, improving regional connectivity.

4

2196 drone frames uploaded — real-time aerial monitoring is active for this project.

Umagaon-Saharsa (Package-V) Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi is a National Highways Authority of India (NHAI) project on 327E in Bihar. The project has an awarded cost of ₹551.51 Cr and is currently ongoing with physical progress at 99.5%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

2,196 frames · NHAI surveillance footage · UPC N/09072/01006/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "Umagaon-Saharsa (Package-V) Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi"?
Current physical progress: 99.5%. Financial progress: 100.0%. Project stage: PCC Issued, CC Pending. On schedule. Scheduled completion: 14-12-2025. Likely completion: 30-09-2026.
QWho is the contractor for this NHAI highway project?
The contractor for Umagaon-Saharsa (Package-V) Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi is Dhariwal Buildtech Limited. The project is under RO-Patna and covers 39.183 km on 327E.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹551.51 Crore. Total capital cost: ₹768.35 Crore. The project is on 327E in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/09072/01006/BR in NHAI?
UPC (Unique Project Code) N/09072/01006/BR refers to "Umagaon-Saharsa (Package-V) Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi" — a National Highway project on 327E in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.