Umagaon-Saharsa (Package-V) Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi
Physical Progress
99.5%
Drone-monitored
Financial Progress
100.0%
Of awarded cost
Awarded Cost
₹552 Cr
Contract value
Length
39.183 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
2111
Aerial captures
Project Progress
Stage
PCC Issued, CC Pending
Due Date
14-12-2025
Likely Date
30-06-2026
Completion
99.5%
Physical Done
Project Timeline
Awarded
15-12-2023
Construction Started
15-12-2023
In Progress
Near Completion
13-09-2025
Completed
30-06-2026
Physical vs Financial Progress
Project Details
UPC
N/09072/01006/BR
National Highway
327E
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
39.183 km
Contractor
Dhariwal Buildtech Limited
Project Stage
PCC Issued, CC Pending
Drone Frames
2111 frames
Last Flight
2026-02-20
Cost & Timeline
Awarded Cost
₹551.51 Cr
Capital Cost
₹768.35 Cr
Start Date
15-12-2023
PCOD Date
13-09-2025
Scheduled Completion
14-12-2025
Likely Completion
30-06-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 16:05:41
Contractor Profile
Dhariwal Buildtech Limited
Project Intelligence
Construction is 99.5% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 39.183 km on 327E, improving regional connectivity.
2111 drone frames uploaded — real-time aerial monitoring is active for this project.
Umagaon-Saharsa (Package-V) Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi is a National Highways Authority of India (NHAI) project on 327E in Bihar. The project has an awarded cost of ₹551.51 Cr and is currently ongoing with physical progress at 99.5%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
2,111 frames · NHAI surveillance footage · UPC N/09072/01006/BR
Frequently Asked Questions
- What is the current status of the NHAI project "Umagaon-Saharsa (Package-V) Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi"?
- Current physical progress: 99.5%. Financial progress: 100.0%. Project stage: PCC Issued, CC Pending. On schedule. Scheduled completion: 14-12-2025. Likely completion: 30-06-2026.
- Who is the contractor for this NHAI highway project?
- The contractor for Umagaon-Saharsa (Package-V) Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi is Dhariwal Buildtech Limited. The project is under RO-Patna and covers 39.183 km on 327E.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹551.51 Crore. Total capital cost: ₹768.35 Crore. The project is on 327E in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/09072/01006/BR in NHAI?
- UPC (Unique Project Code) N/09072/01006/BR refers to "Umagaon-Saharsa (Package-V) Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi" — a National Highway project on 327E in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.