4L of Bahadurganj Araria section from Km 49.000 to Km 94.000 (Package-II) of NH-327E
Physical Progress
100.0%
Drone-monitored
Financial Progress
100.0%
Of awarded cost
Awarded Cost
₹1082 Cr
Contract value
Length
44.995 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
6724
Aerial captures
Project Progress
Stage
CC Issued
Due Date
09-01-2024
Likely Date
28-02-2026
Completion
100.0%
Physical Done
Project Timeline
Awarded
10-01-2022
Construction Started
10-01-2022
In Progress
Near Completion
10-08-2024
Completed
28-02-2026
Physical vs Financial Progress
Project Details
UPC
N/03012/03001/BR
National Highway
327E
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
44.995 km
Contractor
G R Infraprojects Limited
Project Stage
CC Issued
Drone Frames
6724 frames
Last Flight
2025-12-24
Cost & Timeline
Awarded Cost
₹1081.70 Cr
Capital Cost
₹1358.77 Cr
Start Date
10-01-2022
PCOD Date
10-08-2024
Scheduled Completion
09-01-2024
Likely Completion
28-02-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-17 11:55:01
Contractor Profile
G R Infraprojects Limited
Project Intelligence
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 44.995 km on 327E, improving regional connectivity.
6724 drone frames uploaded — real-time aerial monitoring is active for this project.
4L of Bahadurganj Araria section from Km 49.000 to Km 94.000 (Package-II) of NH-327E is a National Highways Authority of India (NHAI) project on 327E in Bihar. The project has an awarded cost of ₹1081.70 Cr and is currently **1** with physical progress at 100.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
6,724 frames · NHAI surveillance footage · UPC N/03012/03001/BR
Frequently Asked Questions
- What is the current status of the NHAI project "4L of Bahadurganj Araria section from Km 49.000 to Km 94.000 (Package-II) of NH-"?
- Current physical progress: 100.0%. Financial progress: 100.0%. Project stage: CC Issued. On schedule. Scheduled completion: 09-01-2024. Likely completion: 28-02-2026.
- Who is the contractor for this NHAI highway project?
- The contractor for 4L of Bahadurganj Araria section from Km 49.000 to Km 94.000 (Package-II) of NH-327E is G R Infraprojects Limited. The project is under RO-Patna and covers 44.995 km on 327E.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹1081.70 Crore. Total capital cost: ₹1358.77 Crore. The project is on 327E in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/03012/03001/BR in NHAI?
- UPC (Unique Project Code) N/03012/03001/BR refers to "4L of Bahadurganj Araria section from Km 49.000 to Km 94.000 (Package-II) of NH-327E" — a National Highway project on 327E in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.