All NHAI Projects
27PBMC 6567 Drone Frames

Routine Maintenance and Major maintenance of four and more lane of Gopalganj-Kotwa section from Km 360.915 to Km 440.000 (existing Km 366.117 to Km 445.202) of NH-28 (New NH-27) in the state of Bihar on PBMC mode.

UPC: N/02022/02006/BR

Physical Progress

0.0%

Drone-monitored

Financial Progress

0.0%

Of awarded cost

Awarded Cost

₹126 Cr

Contract value

Length

76.335 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

6567

Aerial captures

Project Progress

Physical Progress0.0%
Financial Progress0.0%

Stage

Under O&M through OMT/TOT/O&M Agency at Site

Due Date

04-07-2029

Likely Date

-

Completion

0.0%

Physical Done

DoneRemaining

Project Timeline

Awarded

05-07-2024

Construction Started

05-07-2024

In Progress

Near Completion

-

Completed

-

Physical vs Financial Progress

Project Details

UPC

N/02022/02006/BR

National Highway

27

Regional Office

RO-Patna

State

Bihar

Mode

PBMC

Length

76.335 km

Contractor

INCKAH Infrastructure Technologies Pvt. Ltd.

Project Stage

Under O&M through OMT/TOT/O&M Agency at Site

Drone Frames

6567 frames

Last Flight

2026-03-26

Cost & Timeline

Awarded Cost

₹126.20 Cr

Capital Cost

N/A

Start Date

05-07-2024

PCOD Date

-

Scheduled Completion

04-07-2029

Likely Completion

-

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-08-02 15:50:02

Contractor Profile

INCKAH Infrastructure Technologies Pvt. Ltd.

RO-Patna27PBMC

Project Intelligence

1

Physical progress stands at 0.0%. Financial utilization at 0.0%.

2

Project is on schedule or ahead of planned completion date.

3

Covers 76.335 km on 27, improving regional connectivity.

4

6567 drone frames uploaded — real-time aerial monitoring is active for this project.

Routine Maintenance and Major maintenance of four and more lane of Gopalganj-Kotwa section from Km 360.915 to Km 440.000 (existing Km 366.117 to Km 445.202) of NH-28 (New NH-27) in the state of Bihar on PBMC mode. is a National Highways Authority of India (NHAI) project on 27 in Bihar. The project has an awarded cost of ₹126.20 Cr and is currently ongoing with physical progress at 0.0%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

6,567 frames · NHAI surveillance footage · UPC N/02022/02006/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "Routine Maintenance and Major maintenance of four and more lane of Gopalganj-Kot"?
Current physical progress: 0.0%. Financial progress: 0.0%. Project stage: Under O&M through OMT/TOT/O&M Agency at Site. On schedule. Scheduled completion: 04-07-2029. Likely completion: -.
QWho is the contractor for this NHAI highway project?
The contractor for Routine Maintenance and Major maintenance of four and more lane of Gopalganj-Kotwa section from Km 360.915 to Km 440.000 (existing Km 366.117 to Km 445.202) of NH-28 (New NH-27) in the state of Bihar on PBMC mode. is INCKAH Infrastructure Technologies Pvt. Ltd.. The project is under RO-Patna and covers 76.335 km on 27.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹126.20 Crore. The project is on 27 in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/02022/02006/BR in NHAI?
UPC (Unique Project Code) N/02022/02006/BR refers to "Routine Maintenance and Major maintenance of four and more lane of Gopalganj-Kotwa section from Km 360.915 to Km 440.000 (existing Km 366.117 to Km 445.202) of NH-28 (New NH-27) in the state of Bihar on PBMC mode." — a National Highway project on 27 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.