Permanent rectification of 3 nos. of black spots in project Highway NH-27 of U.P border - Dewapur - Kotwa section from Km.360.915 to km.440.000 (Total Length of 79.085 Km) of NH-27& Permanent rectification of 5 nos. of black spots of project Highway NH-27 of Kotwa - Mehsi - Muzaffarpur Section from km.440.000 to km.520.000 (Total length 80.00Km)
Physical Progress
81.0%
Drone-monitored
Financial Progress
78.0%
Of awarded cost
Awarded Cost
₹227 Cr
Contract value
Length
13.604 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
510
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
11-12-2025
Likely Date
31-10-2026
Completion
81.0%
Physical Done
Project Timeline
Awarded
12-12-2023
Construction Started
12-12-2023
In Progress
Near Completion
-
Completed
31-10-2026
Physical vs Financial Progress
Project Details
UPC
N/02023/01003/BR
National Highway
27
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
13.604 km
Contractor
EVRASCON - UARPL JV
Project Stage
Under Construction (AD issued)
Drone Frames
510 frames
Last Flight
2026-03-27
Cost & Timeline
Awarded Cost
₹227.25 Cr
Capital Cost
₹227.25 Cr
Start Date
12-12-2023
PCOD Date
-
Scheduled Completion
11-12-2025
Likely Completion
31-10-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 21:04:36
Contractor Profile
EVRASCON - UARPL JV
Project Intelligence
Construction is 81.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 13.604 km on 27, improving regional connectivity.
510 drone frames uploaded — real-time aerial monitoring is active for this project.
Permanent rectification of 3 nos. of black spots in project Highway NH-27 of U.P border - Dewapur - Kotwa section from Km.360.915 to km.440.000 (Total Length of 79.085 Km) of NH-27& Permanent rectification of 5 nos. of black spots of project Highway NH-27 of Kotwa - Mehsi - Muzaffarpur Section from km.440.000 to km.520.000 (Total length 80.00Km) is a National Highways Authority of India (NHAI) project on 27 in Bihar. The project has an awarded cost of ₹227.25 Cr and is currently **ongoing** with physical progress at 81.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
510 frames · NHAI surveillance footage · UPC N/02023/01003/BR
Frequently Asked Questions
- What is the current status of the NHAI project "Permanent rectification of 3 nos. of black spots in project Highway NH-27 of U.P"?
- Current physical progress: 81.0%. Financial progress: 78.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 11-12-2025. Likely completion: 31-10-2026.
- Who is the contractor for this NHAI highway project?
- The contractor for Permanent rectification of 3 nos. of black spots in project Highway NH-27 of U.P border - Dewapur - Kotwa section from Km.360.915 to km.440.000 (Total Length of 79.085 Km) of NH-27& Permanent rectification of 5 nos. of black spots of project Highway NH-27 of Kotwa - Mehsi - Muzaffarpur Section from km.440.000 to km.520.000 (Total length 80.00Km) is EVRASCON - UARPL JV. The project is under RO-Patna and covers 13.604 km on 27.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹227.25 Crore. Total capital cost: ₹227.25 Crore. The project is on 27 in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/02023/01003/BR in NHAI?
- UPC (Unique Project Code) N/02023/01003/BR refers to "Permanent rectification of 3 nos. of black spots in project Highway NH-27 of U.P border - Dewapur - Kotwa section from Km.360.915 to km.440.000 (Total Length of 79.085 Km) of NH-27& Permanent rectification of 5 nos. of black spots of project Highway NH-27 of Kotwa - Mehsi - Muzaffarpur Section from km.440.000 to km.520.000 (Total length 80.00Km) " — a National Highway project on 27 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.