Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /NHAI Drone Tracker
  3. /Patna Bakhtiyarpur section of NH-30 from km. 181.3
All NHAI Projects
922BOT TollRoad Infrastructure 4286 Drone Frames

Patna Bakhtiyarpur section of NH-30 from km. 181.300 to km. 231.950

UPC: N/08017/01001/BR

Physical Progress

99.8%

Drone-monitored

Financial Progress

99.7%

Of awarded cost

Awarded Cost

₹574 Cr

Contract value

Length

50.45 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

4286

Aerial captures

Project Progress

Physical Progress99.8%
Financial Progress99.7%

Stage

CC Issued

Due Date

24-03-2014

Likely Date

15-01-2026

Completion

99.8%

Physical Done

DoneRemaining

Project Timeline

Awarded

26-09-2011

Construction Started

26-09-2011

In Progress

Near Completion

10-04-2015

Completed

15-01-2026

Physical vs Financial Progress

Project Details

UPC

N/08017/01001/BR

National Highway

922

Regional Office

RO-Patna

State

Bihar

Mode

BOT Toll

Length

50.45 km

Contractor

BSC - C&C (JV)

Project Stage

CC Issued

Drone Frames

4286 frames

Last Flight

2026-02-24

Cost & Timeline

Awarded Cost

₹574.00 Cr

Capital Cost

₹523.75 Cr

Start Date

26-09-2011

PCOD Date

10-04-2015

Scheduled Completion

24-03-2014

Likely Completion

15-01-2026

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-06-18 13:57:55

Contractor Profile

BSC - C&C (JV)

RO-Patna922BOT Toll

Project Intelligence

1

Construction is 99.8% complete — nearing final stages.

2

Project is on schedule or ahead of planned completion date.

3

Covers 50.45 km on 922, improving regional connectivity.

4

4286 drone frames uploaded — real-time aerial monitoring is active for this project.

Drone Imagery Available

4,286 frames · NHAI surveillance footage · UPC N/08017/01001/BR

View Drone Images

Frequently Asked Questions

What is the current status of the NHAI project "Patna Bakhtiyarpur section of NH-30 from km. 181.300 to km. 231.950"?
Current physical progress: 99.8%. Financial progress: 99.7%. Project stage: CC Issued. On schedule. Scheduled completion: 24-03-2014. Likely completion: 15-01-2026.
Who is the contractor for this NHAI highway project?
The contractor for Patna Bakhtiyarpur section of NH-30 from km. 181.300 to km. 231.950 is BSC - C&C (JV). The project is under RO-Patna and covers 50.45 km on 922.
What is the cost of this NHAI highway project?
The awarded cost is ₹574.00 Crore. Total capital cost: ₹523.75 Crore. The project is on 922 in Bihar, monitored via drone surveillance by NHAI.
What is UPC N/08017/01001/BR in NHAI?
UPC (Unique Project Code) N/08017/01001/BR refers to "Patna Bakhtiyarpur section of NH-30 from km. 181.300 to km. 231.950" — a National Highway project on 922 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.

Related Resources

NHAI

NHAI Drone Tracker Dashboard

Real-time drone progress for all NHAI Bihar projects

RCD

Bihar RCD PMIS

State road and bridge project tracker

Roads

Bihar Road Network Map

GIS map of all Bihar highways and roads

Projects

Bihar Infrastructure Projects

All government infrastructure projects

IPM

IPM Central Project Monitor

Central government projects in Bihar

Tenders

Bihar Government Tenders

Procurement notices including road contracts

BRPNNL

BRPNNL Bridge Projects

Bihar bridge and road project monitor

Cabinet

Bihar Cabinet Decisions

Policy approvals for infrastructure