Physical Progress
99.8%
Drone-monitored
Financial Progress
99.7%
Of awarded cost
Awarded Cost
₹574 Cr
Contract value
Length
50.45 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
4286
Aerial captures
Stage
CC Issued
Due Date
24-03-2014
Likely Date
15-01-2026
99.8%
Physical Done
Awarded
26-09-2011
Construction Started
26-09-2011
In Progress
Near Completion
10-04-2015
Completed
15-01-2026
UPC
N/08017/01001/BR
National Highway
922
Regional Office
RO-Patna
State
Bihar
Mode
BOT Toll
Length
50.45 km
Contractor
BSC - C&C (JV)
Project Stage
CC Issued
Drone Frames
4286 frames
Last Flight
2026-02-24
Awarded Cost
₹574.00 Cr
Capital Cost
₹523.75 Cr
Start Date
26-09-2011
PCOD Date
10-04-2015
Scheduled Completion
24-03-2014
Likely Completion
15-01-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 13:57:55
BSC - C&C (JV)
Construction is 99.8% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 50.45 km on 922, improving regional connectivity.
4286 drone frames uploaded — real-time aerial monitoring is active for this project.
4,286 frames · NHAI surveillance footage · UPC N/08017/01001/BR