Patna Bakhtiyarpur section of NH-30 from km. 181.300 to km. 231.950
Physical Progress
99.8%
Drone-monitored
Financial Progress
99.7%
Of awarded cost
Awarded Cost
₹574 Cr
Contract value
Length
50.45 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
4286
Aerial captures
Project Progress
Stage
CC Issued
Due Date
24-03-2014
Likely Date
15-01-2026
Completion
99.8%
Physical Done
Project Timeline
Awarded
26-09-2011
Construction Started
26-09-2011
In Progress
Near Completion
10-04-2015
Completed
15-01-2026
Physical vs Financial Progress
Project Details
UPC
N/08017/01001/BR
National Highway
922
Regional Office
RO-Patna
State
Bihar
Mode
BOT Toll
Length
50.45 km
Contractor
BSC - C&C (JV)
Project Stage
CC Issued
Drone Frames
4286 frames
Last Flight
2026-02-24
Cost & Timeline
Awarded Cost
₹574.00 Cr
Capital Cost
₹523.75 Cr
Start Date
26-09-2011
PCOD Date
10-04-2015
Scheduled Completion
24-03-2014
Likely Completion
15-01-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 13:57:55
Contractor Profile
BSC - C&C (JV)
Project Intelligence
Construction is 99.8% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 50.45 km on 922, improving regional connectivity.
4286 drone frames uploaded — real-time aerial monitoring is active for this project.
Patna Bakhtiyarpur section of NH-30 from km. 181.300 to km. 231.950 is a National Highways Authority of India (NHAI) project on 922 in Bihar. The project has an awarded cost of ₹574.00 Cr and is currently 1 with physical progress at 99.8%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
4,286 frames · NHAI surveillance footage · UPC N/08017/01001/BR
Frequently Asked Questions
- What is the current status of the NHAI project "Patna Bakhtiyarpur section of NH-30 from km. 181.300 to km. 231.950"?
- Current physical progress: 99.8%. Financial progress: 99.7%. Project stage: CC Issued. On schedule. Scheduled completion: 24-03-2014. Likely completion: 15-01-2026.
- Who is the contractor for this NHAI highway project?
- The contractor for Patna Bakhtiyarpur section of NH-30 from km. 181.300 to km. 231.950 is BSC - C&C (JV). The project is under RO-Patna and covers 50.45 km on 922.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹574.00 Crore. Total capital cost: ₹523.75 Crore. The project is on 922 in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/08017/01001/BR in NHAI?
- UPC (Unique Project Code) N/08017/01001/BR refers to "Patna Bakhtiyarpur section of NH-30 from km. 181.300 to km. 231.950" — a National Highway project on 922 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.