Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
All NHAI Projects
922BOT Toll 4286 Drone Frames

Patna Bakhtiyarpur section of NH-30 from km. 181.300 to km. 231.950

UPC: N/08017/01001/BR

Physical Progress

99.8%

Drone-monitored

Financial Progress

99.7%

Of awarded cost

Awarded Cost

₹574 Cr

Contract value

Length

50.45 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

4286

Aerial captures

Project Progress

Physical Progress99.8%
Financial Progress99.7%

Stage

CC Issued

Due Date

24-03-2014

Likely Date

15-01-2026

Completion

99.8%

Physical Done

DoneRemaining

Project Timeline

Awarded

26-09-2011

Construction Started

26-09-2011

In Progress

Near Completion

10-04-2015

Completed

15-01-2026

Physical vs Financial Progress

Project Details

UPC

N/08017/01001/BR

National Highway

922

Regional Office

RO-Patna

State

Bihar

Mode

BOT Toll

Length

50.45 km

Contractor

BSC - C&C (JV)

Project Stage

CC Issued

Drone Frames

4286 frames

Last Flight

2026-02-24

Cost & Timeline

Awarded Cost

₹574.00 Cr

Capital Cost

₹523.75 Cr

Start Date

26-09-2011

PCOD Date

10-04-2015

Scheduled Completion

24-03-2014

Likely Completion

15-01-2026

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-06-18 13:57:55

Contractor Profile

BSC - C&C (JV)

RO-Patna922BOT Toll

Project Intelligence

1

Construction is 99.8% complete — nearing final stages.

2

Project is on schedule or ahead of planned completion date.

3

Covers 50.45 km on 922, improving regional connectivity.

4

4286 drone frames uploaded — real-time aerial monitoring is active for this project.

Patna Bakhtiyarpur section of NH-30 from km. 181.300 to km. 231.950 is a National Highways Authority of India (NHAI) project on 922 in Bihar. The project has an awarded cost of ₹574.00 Cr and is currently 1 with physical progress at 99.8%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

4,286 frames · NHAI surveillance footage · UPC N/08017/01001/BR

View Drone Images

Frequently Asked Questions

What is the current status of the NHAI project "Patna Bakhtiyarpur section of NH-30 from km. 181.300 to km. 231.950"?
Current physical progress: 99.8%. Financial progress: 99.7%. Project stage: CC Issued. On schedule. Scheduled completion: 24-03-2014. Likely completion: 15-01-2026.
Who is the contractor for this NHAI highway project?
The contractor for Patna Bakhtiyarpur section of NH-30 from km. 181.300 to km. 231.950 is BSC - C&C (JV). The project is under RO-Patna and covers 50.45 km on 922.
What is the cost of this NHAI highway project?
The awarded cost is ₹574.00 Crore. Total capital cost: ₹523.75 Crore. The project is on 922 in Bihar, monitored via drone surveillance by NHAI.
What is UPC N/08017/01001/BR in NHAI?
UPC (Unique Project Code) N/08017/01001/BR refers to "Patna Bakhtiyarpur section of NH-30 from km. 181.300 to km. 231.950" — a National Highway project on 922 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.