Bhojpur Buxar section of NH-84 from km.27.37 to km. 75.00
Physical Progress
100.0%
Drone-monitored
Financial Progress
97.2%
Of awarded cost
Awarded Cost
₹682 Cr
Contract value
Length
47.9 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
3905
Aerial captures
Project Progress
Stage
CC Issued
Due Date
01-01-2020
Likely Date
15-05-2023
Completion
100.0%
Physical Done
Project Timeline
Awarded
18-04-2018
Construction Started
18-04-2018
In Progress
Near Completion
16-05-2023
Completed
15-05-2023
Physical vs Financial Progress
Project Details
UPC
N/08067/03001/BR
National Highway
922
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
47.9 km
Contractor
PNC-SPSCPL (JV)
Project Stage
CC Issued
Drone Frames
3905 frames
Last Flight
2026-08-27
Cost & Timeline
Awarded Cost
₹681.67 Cr
Capital Cost
₹1195.18 Cr
Start Date
18-04-2018
PCOD Date
16-05-2023
Scheduled Completion
01-01-2020
Likely Completion
15-05-2023
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-09-13 18:41:26
Contractor Profile
PNC-SPSCPL (JV)
Project Intelligence
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 47.9 km on 922, improving regional connectivity.
3905 drone frames uploaded — real-time aerial monitoring is active for this project.
Bhojpur Buxar section of NH-84 from km.27.37 to km. 75.00 is a National Highways Authority of India (NHAI) project on 922 in Bihar. The project has an awarded cost of ₹681.67 Cr and is currently 1 with physical progress at 100.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
3,905 frames · NHAI surveillance footage · UPC N/08067/03001/BR
Frequently Asked Questions
- QWhat is the current status of the NHAI project "Bhojpur Buxar section of NH-84 from km.27.37 to km. 75.00"?
- Current physical progress: 100.0%. Financial progress: 97.2%. Project stage: CC Issued. On schedule. Scheduled completion: 01-01-2020. Likely completion: 15-05-2023.
- QWho is the contractor for this NHAI highway project?
- The contractor for Bhojpur Buxar section of NH-84 from km.27.37 to km. 75.00 is PNC-SPSCPL (JV). The project is under RO-Patna and covers 47.9 km on 922.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹681.67 Crore. Total capital cost: ₹1195.18 Crore. The project is on 922 in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/08067/03001/BR in NHAI?
- UPC (Unique Project Code) N/08067/03001/BR refers to "Bhojpur Buxar section of NH-84 from km.27.37 to km. 75.00" — a National Highway project on 922 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.