922EPC 3905 Drone Frames

Bhojpur Buxar section of NH-84 from km.27.37 to km. 75.00

UPC: N/08067/03001/BR

Physical Progress

100.0%

Drone-monitored

Financial Progress

97.2%

Of awarded cost

Awarded Cost

₹682 Cr

Contract value

Length

47.9 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

3905

Aerial captures

Project Progress

Physical Progress100.0%
Financial Progress97.2%

Stage

CC Issued

Due Date

01-01-2020

Likely Date

15-05-2023

Completion

100.0%

Physical Done

DoneRemaining

Project Timeline

Awarded

18-04-2018

Construction Started

18-04-2018

In Progress

Near Completion

16-05-2023

Completed

15-05-2023

Physical vs Financial Progress

Project Details

UPC

N/08067/03001/BR

National Highway

922

Regional Office

RO-Patna

State

Bihar

Mode

EPC

Length

47.9 km

Contractor

PNC-SPSCPL (JV)

Project Stage

CC Issued

Drone Frames

3905 frames

Last Flight

2026-08-27

Cost & Timeline

Awarded Cost

₹681.67 Cr

Capital Cost

₹1195.18 Cr

Start Date

18-04-2018

PCOD Date

16-05-2023

Scheduled Completion

01-01-2020

Likely Completion

15-05-2023

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-13 18:41:26

Contractor Profile

PNC-SPSCPL (JV)

RO-Patna922EPC

Project Intelligence

1

Construction is 100.0% complete — nearing final stages.

2

Project is on schedule or ahead of planned completion date.

3

Covers 47.9 km on 922, improving regional connectivity.

4

3905 drone frames uploaded — real-time aerial monitoring is active for this project.

Bhojpur Buxar section of NH-84 from km.27.37 to km. 75.00 is a National Highways Authority of India (NHAI) project on 922 in Bihar. The project has an awarded cost of ₹681.67 Cr and is currently 1 with physical progress at 100.0%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

3,905 frames · NHAI surveillance footage · UPC N/08067/03001/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "Bhojpur Buxar section of NH-84 from km.27.37 to km. 75.00"?
Current physical progress: 100.0%. Financial progress: 97.2%. Project stage: CC Issued. On schedule. Scheduled completion: 01-01-2020. Likely completion: 15-05-2023.
QWho is the contractor for this NHAI highway project?
The contractor for Bhojpur Buxar section of NH-84 from km.27.37 to km. 75.00 is PNC-SPSCPL (JV). The project is under RO-Patna and covers 47.9 km on 922.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹681.67 Crore. Total capital cost: ₹1195.18 Crore. The project is on 922 in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/08067/03001/BR in NHAI?
UPC (Unique Project Code) N/08067/03001/BR refers to "Bhojpur Buxar section of NH-84 from km.27.37 to km. 75.00" — a National Highway project on 922 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.