Physical Progress
100.0%
Drone-monitored
Financial Progress
97.2%
Of awarded cost
Awarded Cost
₹682 Cr
Contract value
Length
47.9 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
3979
Aerial captures
Stage
CC Issued
Due Date
01-01-2020
Likely Date
15-05-2023
100.0%
Physical Done
Awarded
18-04-2018
Construction Started
18-04-2018
In Progress
Near Completion
16-05-2023
Completed
15-05-2023
UPC
N/08067/03001/BR
National Highway
922
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
47.9 km
Contractor
PNC-SPSCPL (JV)
Project Stage
CC Issued
Drone Frames
3979 frames
Last Flight
2026-02-24
Awarded Cost
₹681.67 Cr
Capital Cost
₹1195.18 Cr
Start Date
18-04-2018
PCOD Date
16-05-2023
Scheduled Completion
01-01-2020
Likely Completion
15-05-2023
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 13:50:15
PNC-SPSCPL (JV)
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 47.9 km on 922, improving regional connectivity.
3979 drone frames uploaded — real-time aerial monitoring is active for this project.
3,979 frames · NHAI surveillance footage · UPC N/08067/03001/BR