Physical Progress
22.4%
Drone-monitored
Financial Progress
13.0%
Of awarded cost
Awarded Cost
₹268 Cr
Contract value
Length
5 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
440
Aerial captures
Stage
Under Construction (AD issued)
Due Date
30-04-2027
Likely Date
16-03-2028
22.4%
Physical Done
Awarded
30-10-2024
Construction Started
30-10-2024
In Progress
Near Completion
-
Completed
16-03-2028
UPC
N/09074/01002/BR
National Highway
527C
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
5 km
Contractor
ASC Infratech Pvt. Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
440 frames
Last Flight
2026-04-26
Awarded Cost
₹268.00 Cr
Capital Cost
₹498.97 Cr
Start Date
30-10-2024
PCOD Date
-
Scheduled Completion
30-04-2027
Likely Completion
16-03-2028
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 18:05:27
ASC Infratech Pvt. Ltd.
Physical progress stands at 22.4%. Financial utilization at 13.0%.
Project is on schedule or ahead of planned completion date.
Covers 5 km on 527C, improving regional connectivity.
440 drone frames uploaded — real-time aerial monitoring is active for this project.
440 frames · NHAI surveillance footage · UPC N/09074/01002/BR