Construction of Major Bridge over Baghmati and Lakhandei River along with Approaches from Design km.16.500 to km.21.500
Physical Progress
26.8%
Drone-monitored
Financial Progress
17.1%
Of awarded cost
Awarded Cost
₹268 Cr
Contract value
Length
5 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
494
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
30-04-2027
Likely Date
16-03-2028
Completion
26.8%
Physical Done
Project Timeline
Awarded
30-10-2024
Construction Started
30-10-2024
In Progress
Near Completion
-
Completed
16-03-2028
Physical vs Financial Progress
Project Details
UPC
N/09074/01002/BR
National Highway
527C
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
5 km
Contractor
ASC Infratech Pvt. Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
494 frames
Last Flight
2026-08-27
Cost & Timeline
Awarded Cost
₹268.00 Cr
Capital Cost
₹498.97 Cr
Start Date
30-10-2024
PCOD Date
-
Scheduled Completion
30-04-2027
Likely Completion
16-03-2028
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-09-13 14:13:22
Contractor Profile
ASC Infratech Pvt. Ltd.
Project Intelligence
Physical progress stands at 26.8%. Financial utilization at 17.1%.
Project is on schedule or ahead of planned completion date.
Covers 5 km on 527C, improving regional connectivity.
494 drone frames uploaded — real-time aerial monitoring is active for this project.
Construction of Major Bridge over Baghmati and Lakhandei River along with Approaches from Design km.16.500 to km.21.500 is a National Highways Authority of India (NHAI) project on 527C in Bihar. The project has an awarded cost of ₹268.00 Cr and is currently ongoing with physical progress at 26.8%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
494 frames · NHAI surveillance footage · UPC N/09074/01002/BR
Frequently Asked Questions
- QWhat is the current status of the NHAI project "Construction of Major Bridge over Baghmati and Lakhandei River along with Approa"?
- Current physical progress: 26.8%. Financial progress: 17.1%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 30-04-2027. Likely completion: 16-03-2028.
- QWho is the contractor for this NHAI highway project?
- The contractor for Construction of Major Bridge over Baghmati and Lakhandei River along with Approaches from Design km.16.500 to km.21.500 is ASC Infratech Pvt. Ltd.. The project is under RO-Patna and covers 5 km on 527C.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹268.00 Crore. Total capital cost: ₹498.97 Crore. The project is on 527C in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/09074/01002/BR in NHAI?
- UPC (Unique Project Code) N/09074/01002/BR refers to "Construction of Major Bridge over Baghmati and Lakhandei River along with Approaches from Design km.16.500 to km.21.500" — a National Highway project on 527C in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.