Physical Progress
99.8%
Drone-monitored
Financial Progress
84.9%
Of awarded cost
Awarded Cost
₹537 Cr
Contract value
Length
63.66 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
3415
Aerial captures
Stage
Under Construction (AD issued)
Due Date
04-11-2021
Likely Date
30-06-2026
99.8%
Physical Done
Awarded
05-11-2019
Construction Started
05-11-2019
In Progress
Near Completion
-
Completed
30-06-2026
UPC
N/09074/01001/BR
National Highway
527C
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
63.66 km
Contractor
Ram Kripal Singh Construction Pvt. Ltd
Project Stage
Under Construction (AD issued)
Drone Frames
3415 frames
Last Flight
2026-01-27
Awarded Cost
₹537.17 Cr
Capital Cost
₹638.29 Cr
Start Date
05-11-2019
PCOD Date
-
Scheduled Completion
04-11-2021
Likely Completion
30-06-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 18:02:37
Ram Kripal Singh Construction Pvt. Ltd
Construction is 99.8% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 63.66 km on 527C, improving regional connectivity.
3415 drone frames uploaded — real-time aerial monitoring is active for this project.
3,415 frames · NHAI surveillance footage · UPC N/09074/01001/BR