Physical Progress
100.0%
Drone-monitored
Financial Progress
95.1%
Of awarded cost
Awarded Cost
₹690 Cr
Contract value
Length
60.8 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
6893
Aerial captures
Stage
CC Issued
Due Date
16-07-2023
Likely Date
30-11-2025
100.0%
Physical Done
Awarded
16-01-2021
Construction Started
16-01-2021
In Progress
Near Completion
-
Completed
30-11-2025
UPC
N/05056/01003/BR
National Highway
319
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
60.8 km
Contractor
Ashoka Buildcon Limited
Project Stage
CC Issued
Drone Frames
6893 frames
Last Flight
2026-02-23
Awarded Cost
₹690.00 Cr
Capital Cost
₹984.63 Cr
Start Date
16-01-2021
PCOD Date
-
Scheduled Completion
16-07-2023
Likely Completion
30-11-2025
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 12:06:50
Ashoka Buildcon Limited
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 60.8 km on 319, improving regional connectivity.
6893 drone frames uploaded — real-time aerial monitoring is active for this project.
6,893 frames · NHAI surveillance footage · UPC N/05056/01003/BR