Physical Progress
100.0%
Drone-monitored
Financial Progress
99.7%
Of awarded cost
Awarded Cost
₹700 Cr
Contract value
Length
54.75 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
7725
Aerial captures
Stage
CC Issued
Due Date
25-07-2023
Likely Date
17-07-2023
100.0%
Physical Done
Awarded
16-01-2021
Construction Started
16-01-2021
In Progress
Near Completion
-
Completed
17-07-2023
UPC
N/05056/01002/BR
National Highway
319
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
54.75 km
Contractor
Ashoka Buildcon Limited
Project Stage
CC Issued
Drone Frames
7725 frames
Last Flight
2025-10-21
Awarded Cost
₹700.00 Cr
Capital Cost
₹982.81 Cr
Start Date
16-01-2021
PCOD Date
-
Scheduled Completion
25-07-2023
Likely Completion
17-07-2023
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 11:41:29
Ashoka Buildcon Limited
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 54.75 km on 319, improving regional connectivity.
7725 drone frames uploaded — real-time aerial monitoring is active for this project.
7,725 frames · NHAI surveillance footage · UPC N/05056/01002/BR