Ara - Mohania (Pkg-I)

UPC: N/05056/01002/BR

Physical Progress

100.0%

Drone-monitored

Financial Progress

99.7%

Of awarded cost

Awarded Cost

₹700 Cr

Contract value

Length

54.75 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

4254

Aerial captures

Project Progress

Physical Progress100.0%
Financial Progress99.7%

Stage

CC Issued

Due Date

25-07-2023

Likely Date

17-07-2023

Completion

100.0%

Physical Done

DoneRemaining

Project Timeline

Awarded

16-01-2021

Construction Started

16-01-2021

In Progress

Near Completion

-

Completed

17-07-2023

Physical vs Financial Progress

Project Details

UPC

N/05056/01002/BR

National Highway

319

Regional Office

RO-Patna

State

Bihar

Mode

EPC

Length

54.75 km

Contractor

Ashoka Buildcon Limited

Project Stage

CC Issued

Drone Frames

4254 frames

Last Flight

2026-04-26

Cost & Timeline

Awarded Cost

₹700.00 Cr

Capital Cost

₹982.81 Cr

Start Date

16-01-2021

PCOD Date

-

Scheduled Completion

25-07-2023

Likely Completion

17-07-2023

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-08-03 13:28:56

Contractor Profile

Ashoka Buildcon Limited

RO-Patna319EPC

Project Intelligence

1

Construction is 100.0% complete — nearing final stages.

2

Project is on schedule or ahead of planned completion date.

3

Covers 54.75 km on 319, improving regional connectivity.

4

4254 drone frames uploaded — real-time aerial monitoring is active for this project.

Ara - Mohania (Pkg-I) is a National Highways Authority of India (NHAI) project on 319 in Bihar. The project has an awarded cost of ₹700.00 Cr and is currently 1 with physical progress at 100.0%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

4,254 frames · NHAI surveillance footage · UPC N/05056/01002/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "Ara - Mohania (Pkg-I)"?
Current physical progress: 100.0%. Financial progress: 99.7%. Project stage: CC Issued. On schedule. Scheduled completion: 25-07-2023. Likely completion: 17-07-2023.
QWho is the contractor for this NHAI highway project?
The contractor for Ara - Mohania (Pkg-I) is Ashoka Buildcon Limited. The project is under RO-Patna and covers 54.75 km on 319.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹700.00 Crore. Total capital cost: ₹982.81 Crore. The project is on 319 in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/05056/01002/BR in NHAI?
UPC (Unique Project Code) N/05056/01002/BR refers to "Ara - Mohania (Pkg-I)" — a National Highway project on 319 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.