Roads & HighwaysIPM · Central Project#617916

Work of 6 laning/Construction of elevated corridor from km 0/0 to 10/170 Narol Junction to Sarkhej junction including 4 lane Shastri Bridge on Sabarmati river on NH 47 in the State of Gujarat on HAM mode

Ministry of Road Transport & HighwaysGujarat
Revised Cost: ₹1295 CrUtilization: 13.9%

Original Cost

₹1295 Cr

Baseline estimate

On budget

Revised Cost

₹1295 Cr

Latest approved cost

Expenditure

₹179 Cr

Spent to date

Utilization

13.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1116 Cr

Budget left

Budget Utilization

13.9%
0%25%50%75%100%

Spent

₹179 Cr

Remaining

₹1116 Cr

Total

₹1295 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

15/02/2028

Revised Completion

15/02/2028

Completed

Project Details

Project Code617916
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹1295 Cr
Revised Cost₹1295 Cr
Expenditure₹179 Cr
Original End Date15/02/2028
Revised Date15/02/2028

Project Intelligence

Project is within original budget of ₹1295 Cr — no cost escalation recorded.

Expenditure stands at ₹179 Cr, which is 13.9% of the revised project cost.

Remaining budget: ₹1116 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Work of 6 laning/Construction of elevated corridor from km 0/0 to 10/170 Narol Junction to Sarkhej junction including 4 lane Shastri Bridge on Sabarmati river on NH 47 in the State of Gujarat on HAM mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1295.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Work of 6 laning/Construction of elevated corridor from km 0/0 to 10/170 Narol J"?
Work of 6 laning/Construction of elevated corridor from km 0/0 to 10/170 Narol Junction to Sarkhej junction including 4 lane Shastri Bridge on Sabarmati river on NH 47 in the State of Gujarat on HAM mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹1295 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹1295 Cr has not been significantly revised. Expenditure: ₹179 Cr (13.9% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Work of 6 laning/Construction of elevated corridor from km 0 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617916. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Work of 6 laning/Construction of elevated corridor from km 0 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.