Roads & HighwaysIPM · Central Project#618313

Widening/lmprovement of Existing 2 lane to 4-Laning of Karimganj-Silchar section of NH-37 from Design Ch 0.000 near Silchar ISBT to Design Ch 15.970 near Kalinagar Pt I on NH-37 in Assam on HAM Mode Pkg-1

Ministry of Road Transport & HighwaysAssam
Revised Cost: ₹1182 CrUtilization: 15.1%

Original Cost

₹1182 Cr

Baseline estimate

On budget

Revised Cost

₹1182 Cr

Latest approved cost

Expenditure

₹179 Cr

Spent to date

Utilization

15.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1003 Cr

Budget left

Budget Utilization

15.1%
0%25%50%75%100%

Spent

₹179 Cr

Remaining

₹1003 Cr

Total

₹1182 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

17/09/2027

Revised Completion

17/09/2027

Completed

Project Details

Project Code618313
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAssam
Data Month2026-08

Financial Summary

Original Cost₹1182 Cr
Revised Cost₹1182 Cr
Expenditure₹179 Cr
Original End Date17/09/2027
Revised Date17/09/2027

Project Intelligence

Project is within original budget of ₹1182 Cr — no cost escalation recorded.

Expenditure stands at ₹179 Cr, which is 15.1% of the revised project cost.

Remaining budget: ₹1003 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening/lmprovement of Existing 2 lane to 4-Laning of Karimganj-Silchar section of NH-37 from Design Ch 0.000 near Silchar ISBT to Design Ch 15.970 near Kalinagar Pt I on NH-37 in Assam on HAM Mode Pkg-1 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1182.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening/lmprovement of Existing 2 lane to 4-Laning of Karimganj-Silchar section"?
Widening/lmprovement of Existing 2 lane to 4-Laning of Karimganj-Silchar section of NH-37 from Design Ch 0.000 near Silchar ISBT to Design Ch 15.970 near Kalinagar Pt I on NH-37 in Assam on HAM Mode Pkg-1 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹1182 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹1182 Cr has not been significantly revised. Expenditure: ₹179 Cr (15.1% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening/lmprovement of Existing 2 lane to 4-Laning of Karim is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618313. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening/lmprovement of Existing 2 lane to 4-Laning of Karim is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.