Original Cost
₹287 Cr
Baseline estimate
Revised Cost
₹287 Cr
Latest approved cost
Expenditure
₹187 Cr
Spent to date
Utilization
65.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹100 Cr
Budget left
Spent
₹187 Cr
Remaining
₹100 Cr
Total
₹287 Cr
Project Approved
Construction / Implementation
Original End Date
25/10/2025
Revised Completion
31/01/2026
Completed
Project is within original budget of ₹287 Cr — no cost escalation recorded.
Expenditure stands at ₹187 Cr, which is 65.0% of the revised project cost.
Remaining budget: ₹100 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.