Widening/Improvement to 4-Lane with Paved Shoulder configuration of existing single lane road from Srirampur near Bhairiguri Village to Kachukhana Harichara Paglagaunj Package-I of Srirampur - Dhubri Section of NH-127B from existing Km 0.000 to Km 28.050 Design Km 0.000 to Km 27.650, Design Length27.650 Km under JICA ODA Loan assistance Phase-V -Balance work
Original Cost
₹614 Cr
Baseline estimate
Revised Cost
₹614 Cr
Latest approved cost
Expenditure
₹386 Cr
Spent to date
Utilization
62.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹228 Cr
Budget left
Budget Utilization
62.8%Spent
₹386 Cr
Remaining
₹228 Cr
Total
₹614 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
25/11/2026
Revised Completion
25/11/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹614 Cr — no cost escalation recorded.
Expenditure stands at ₹386 Cr, which is 62.8% of the revised project cost.
Remaining budget: ₹228 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening/Improvement to 4-Lane with Paved Shoulder configuration of existing single lane road from Srirampur near Bhairiguri Village to Kachukhana Harichara Paglagaunj Package-I of Srirampur - Dhubri Section of NH-127B from existing Km 0.000 to Km 28.050 Design Km 0.000 to Km 27.650, Design Length27.650 Km under JICA ODA Loan assistance Phase-V -Balance work is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹614.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening/Improvement to 4-Lane with Paved Shoulder configuration of existing sin"?
- Widening/Improvement to 4-Lane with Paved Shoulder configuration of existing single lane road from Srirampur near Bhairiguri Village to Kachukhana Harichara Paglagaunj Package-I of Srirampur - Dhubri Section of NH-127B from existing Km 0.000 to Km 28.050 Design Km 0.000 to Km 27.650, Design Length27.650 Km under JICA ODA Loan assistance Phase-V -Balance work is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹614 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹614 Cr has not been significantly revised. Expenditure: ₹386 Cr (62.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening/Improvement to 4-Lane with Paved Shoulder configura is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618371. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening/Improvement to 4-Lane with Paved Shoulder configura is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.