Widening/Improvement to 2 lane with earthen shoulder of Marrem Khullen to Jessami section of NH-202 of Imphal - Ukhrul - Jessami Economic Corridor from Design Chainage km 95.700 to km 140.180 in the State of Manipur on EPC mode under Bharatmala Pariyojana under NHO-NE Package-6
Original Cost
₹555 Cr
Baseline estimate
Revised Cost
₹555 Cr
Latest approved cost
Expenditure
₹230 Cr
Spent to date
Utilization
41.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹325 Cr
Budget left
Budget Utilization
41.4%Spent
₹230 Cr
Remaining
₹325 Cr
Total
₹555 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
07/12/2026
Revised Completion
02/08/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹555 Cr — no cost escalation recorded.
Expenditure stands at ₹230 Cr, which is 41.4% of the revised project cost.
Remaining budget: ₹325 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening/Improvement to 2 lane with earthen shoulder of Marrem Khullen to Jessami section of NH-202 of Imphal - Ukhrul - Jessami Economic Corridor from Design Chainage km 95.700 to km 140.180 in the State of Manipur on EPC mode under Bharatmala Pariyojana under NHO-NE Package-6 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹555.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening/Improvement to 2 lane with earthen shoulder of Marrem Khullen to Jessam"?
- Widening/Improvement to 2 lane with earthen shoulder of Marrem Khullen to Jessami section of NH-202 of Imphal - Ukhrul - Jessami Economic Corridor from Design Chainage km 95.700 to km 140.180 in the State of Manipur on EPC mode under Bharatmala Pariyojana under NHO-NE Package-6 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Manipur. Original cost: ₹555 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹555 Cr has not been significantly revised. Expenditure: ₹230 Cr (41.4% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening/Improvement to 2 lane with earthen shoulder of Marr is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618305. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening/Improvement to 2 lane with earthen shoulder of Marr is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.