Original Cost
₹1187 Cr
Baseline estimate
Revised Cost
₹1265 Cr
Latest approved cost
Expenditure
₹716 Cr
Spent to date
Utilization
56.6%
Of revised budget
Cost Status
+6.6%
+₹78 Cr increase
Remaining
₹550 Cr
Budget left
Spent
₹716 Cr
Remaining
₹550 Cr
Total
₹1265 Cr
Original Cost
₹1187 Cr
Revised Cost
₹1265 Cr
Increase
+₹78 Cr
Escalation
+6.6%
Project Approved
Construction / Implementation
Original End Date
25/06/2025
Revised Completion
31/03/2027
Completed
Cost has increased by ₹78 Cr (6.6%) from the original estimate of ₹1187 Cr.
Expenditure stands at ₹716 Cr, which is 56.6% of the revised project cost.
Remaining budget: ₹550 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.