from Km. 143.200 to Km. 159.255 Pkg-1
Original Cost
₹470 Cr
Baseline estimate
Revised Cost
₹528 Cr
Latest approved cost
Expenditure
₹243 Cr
Spent to date
Utilization
46.0%
Of revised cost
Cost Overrun
+12.4%
+₹58 Cr
Remaining
₹285 Cr
Budget left
Spent
₹243 Cr
Remaining
₹285 Cr
Total
₹528 Cr
46.0%
Utilized
Original Cost
₹470 Cr
Revised Cost
₹528 Cr
Increase
+₹58 Cr
Escalation
+12.4%
Project Approved
Construction / Implementation
Original End Date
2026-08-29
Revised Completion
2026-08-30
Completed
Cost has increased by ₹58 Cr (12.4%) from the original estimate of ₹470 Cr.
Expenditure stands at ₹243 Cr, which is 46.0% of the revised project cost.
Remaining budget: ₹285 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.