Roads & HighwaysIPM · Central Project +12.4% overrun#618905

Widening with additional 3L abetting Chhapra Bypass Section of NH-19 from Km. 143.200 to Km. 159.255 Pkg-1

Ministry of Road Transport & HighwaysBihar
Revised Cost: ₹528 CrUtilization: 60.3%Overrun: +₹58 Cr

Original Cost

₹470 Cr

Baseline estimate

+12% overrun

Revised Cost

₹528 Cr

Latest approved cost

Expenditure

₹319 Cr

Spent to date

Utilization

60.3%

Of revised budget

Escalated

Cost Status

+12.4%

+₹58 Cr increase

Remaining

₹210 Cr

Budget left

Budget Utilization

60.3%
0%25%50%75%100%

Spent

₹319 Cr

Remaining

₹210 Cr

Total

₹528 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹470 Cr

Revised Cost

₹528 Cr

Increase

+₹58 Cr

Escalation

+12.4%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

29/08/2026

Revised Completion

28/10/2026

Completed

Project Details

Project Code618905
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateBihar
Data Month2026-08

Financial Summary

Original Cost₹470 Cr
Revised Cost₹528 Cr
Expenditure₹319 Cr
Original End Date29/08/2026
Revised Date28/10/2026

Project Intelligence

Cost has increased by ₹58 Cr (12.4%) from the original estimate of ₹470 Cr.

Expenditure stands at ₹319 Cr, which is 60.3% of the revised project cost.

Remaining budget: ₹210 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening with additional 3L abetting Chhapra Bypass Section of NH-19 from Km. 143.200 to Km. 159.255 Pkg-1 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹470.00 Cr, later revised to ₹528.48 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening with additional 3L abetting Chhapra Bypass Section of NH-19 from Km. 14"?
Widening with additional 3L abetting Chhapra Bypass Section of NH-19 from Km. 143.200 to Km. 159.255 Pkg-1 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹470 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹470 Cr and has been revised to ₹528 Cr — a cost overrun of +12.4%. Expenditure to date: ₹319 Cr (60.3% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening with additional 3L abetting Chhapra Bypass Section is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618905. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening with additional 3L abetting Chhapra Bypass Section is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.