Widening & Upgradation to 2-lanes with paved shoulders road from Tamenglong to Mahur NH-137 in the State of Assam starting from km 116.480 near Hangrum to km 136.500 near Hejaichak Package-8 on EPC mode under NHO-NE Package 8
Original Cost
₹904 Cr
Baseline estimate
Revised Cost
₹904 Cr
Latest approved cost
Expenditure
₹564 Cr
Spent to date
Utilization
62.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹340 Cr
Budget left
Budget Utilization
62.3%Spent
₹564 Cr
Remaining
₹340 Cr
Total
₹904 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
29/08/2025
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹904 Cr — no cost escalation recorded.
Expenditure stands at ₹564 Cr, which is 62.3% of the revised project cost.
Remaining budget: ₹340 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening & Upgradation to 2-lanes with paved shoulders road from Tamenglong to Mahur NH-137 in the State of Assam starting from km 116.480 near Hangrum to km 136.500 near Hejaichak Package-8 on EPC mode under NHO-NE Package 8 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹904.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening & Upgradation to 2-lanes with paved shoulders road from Tamenglong to "?
- Widening & Upgradation to 2-lanes with paved shoulders road from Tamenglong to Mahur NH-137 in the State of Assam starting from km 116.480 near Hangrum to km 136.500 near Hejaichak Package-8 on EPC mode under NHO-NE Package 8 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹904 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹904 Cr has not been significantly revised. Expenditure: ₹564 Cr (62.3% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening & Upgradation to 2-lanes with paved shoulders road is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618353. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening & Upgradation to 2-lanes with paved shoulders road is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.