Original Cost
₹446 Cr
Baseline estimate
Revised Cost
₹446 Cr
Latest approved cost
Expenditure
₹18 Cr
Spent to date
Utilization
4.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹428 Cr
Budget left
Spent
₹18 Cr
Remaining
₹428 Cr
Total
₹446 Cr
Project Approved
Construction / Implementation
Original End Date
31/01/2027
Revised Completion
31/01/2027
Completed
Project is within original budget of ₹446 Cr — no cost escalation recorded.
Expenditure stands at ₹18 Cr, which is 4.1% of the revised project cost.
Remaining budget: ₹428 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.