Widening to two/four lane with paved shoulder from Km.180.600 to Km.223.000 of NH-63 on Nizamabad-Jagadalpur road on EPC mode under NHO in the state of Telangana.
Original Cost
₹254 Cr
Baseline estimate
Revised Cost
₹183 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹183 Cr
Budget left
Budget Utilization
0.0%Spent
₹0 Cr
Remaining
₹183 Cr
Total
₹183 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
28/03/2019
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹254 Cr — no cost escalation recorded.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹183 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening to two/four lane with paved shoulder from Km.180.600 to Km.223.000 of NH-63 on Nizamabad-Jagadalpur road on EPC mode under NHO in the state of Telangana. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹254.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening to two/four lane with paved shoulder from Km.180.600 to Km.223.000 of N"?
- Widening to two/four lane with paved shoulder from Km.180.600 to Km.223.000 of NH-63 on Nizamabad-Jagadalpur road on EPC mode under NHO in the state of Telangana. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Telangana. Original cost: ₹254 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹254 Cr and has been revised to ₹183 Cr — a cost overrun of -27.9%. Expenditure to date: ₹0 Cr (N/A% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening to two/four lane with paved shoulder from Km.180.60 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617936. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to two/four lane with paved shoulder from Km.180.60 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.