Widening to two lane with paved Shoulders from Km 40.00 to Km 75.00 Existing chainages of Mangalore - Tumkur section of NH-73 in the State of Karnataka on EPC Mode under Annual Plan 2021-22 Job No NH-73-KNT-2021-22-945

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹719 CrUtilization: 72.7%

Original Cost

₹719 Cr

Baseline estimate

On budget

Revised Cost

₹719 Cr

Latest approved cost

Expenditure

₹523 Cr

Spent to date

Utilization

72.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹196 Cr

Budget left

Budget Utilization

72.7%
0%25%50%75%100%

Spent

₹523 Cr

Remaining

₹196 Cr

Total

₹719 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

26/03/2025

Revised Completion

31/12/2026

Completed

Project Details

Project Code617955
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹719 Cr
Revised Cost₹719 Cr
Expenditure₹523 Cr
Original End Date26/03/2025
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹719 Cr — no cost escalation recorded.

Expenditure stands at ₹523 Cr, which is 72.7% of the revised project cost.

Remaining budget: ₹196 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening to two lane with paved Shoulders from Km 40.00 to Km 75.00 Existing chainages of Mangalore - Tumkur section of NH-73 in the State of Karnataka on EPC Mode under Annual Plan 2021-22 Job No NH-73-KNT-2021-22-945 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹719.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening to two lane with paved Shoulders from Km 40.00 to Km 75.00 Existing c"?
Widening to two lane with paved Shoulders from Km 40.00 to Km 75.00 Existing chainages of Mangalore - Tumkur section of NH-73 in the State of Karnataka on EPC Mode under Annual Plan 2021-22 Job No NH-73-KNT-2021-22-945 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹719 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹719 Cr has not been significantly revised. Expenditure: ₹523 Cr (72.7% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening to two lane with paved Shoulders from Km 40.00 to K is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617955. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to two lane with paved Shoulders from Km 40.00 to K is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.