Original Cost
₹513 Cr
Baseline estimate
Revised Cost
₹513 Cr
Latest approved cost
Expenditure
₹118 Cr
Spent to date
Utilization
22.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹395 Cr
Budget left
Spent
₹118 Cr
Remaining
₹395 Cr
Total
₹513 Cr
Project Approved
Construction / Implementation
Original End Date
19/02/2026
Revised Completion
23/03/2027
Completed
Project is within original budget of ₹513 Cr — no cost escalation recorded.
Expenditure stands at ₹118 Cr, which is 22.9% of the revised project cost.
Remaining budget: ₹395 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.