Widening to Two Lane with Paved Shoulders from Km 0.00 Design Chainage 0.00 to Km 23.338 Design Chainage 23310 of NH-166E MH/KNT Border- Kanamadi- Bijjargi- Tikota section in the state of Karnataka in EPC Mode under Annual plan 2022-23 NH-166E-KNT-2022-23-974
Original Cost
₹196 Cr
Baseline estimate
Revised Cost
₹196 Cr
Latest approved cost
Expenditure
₹82 Cr
Spent to date
Utilization
42.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹114 Cr
Budget left
Budget Utilization
42.0%Spent
₹82 Cr
Remaining
₹114 Cr
Total
₹196 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
05/03/2026
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹196 Cr — no cost escalation recorded.
Expenditure stands at ₹82 Cr, which is 42.0% of the revised project cost.
Remaining budget: ₹114 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening to Two Lane with Paved Shoulders from Km 0.00 Design Chainage 0.00 to Km 23.338 Design Chainage 23310 of NH-166E MH/KNT Border- Kanamadi- Bijjargi- Tikota section in the state of Karnataka in EPC Mode under Annual plan 2022-23 NH-166E-KNT-2022-23-974 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹196.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening to Two Lane with Paved Shoulders from Km 0.00 Design Chainage 0.00 to K"?
- Widening to Two Lane with Paved Shoulders from Km 0.00 Design Chainage 0.00 to Km 23.338 Design Chainage 23310 of NH-166E MH/KNT Border- Kanamadi- Bijjargi- Tikota section in the state of Karnataka in EPC Mode under Annual plan 2022-23 NH-166E-KNT-2022-23-974 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹196 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹196 Cr has not been significantly revised. Expenditure: ₹82 Cr (42.0% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening to Two Lane with Paved Shoulders from Km 0.00 Desig is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618095. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to Two Lane with Paved Shoulders from Km 0.00 Desig is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.