Roads & HighwaysIPM · Central Project#618072

Widening to Existing single lane /intermediate lane to 2 lane from Km185.00 to Km 220.00 of NH-61 New NH-02 in the state of Nagaland.

Ministry of Road Transport & HighwaysNagaland
Revised Cost: ₹297 CrUtilization: 52.2%

Original Cost

₹297 Cr

Baseline estimate

On budget

Revised Cost

₹297 Cr

Latest approved cost

Expenditure

₹155 Cr

Spent to date

Utilization

52.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹142 Cr

Budget left

Budget Utilization

52.2%
0%25%50%75%100%

Spent

₹155 Cr

Remaining

₹142 Cr

Total

₹297 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

20/07/2024

Revised Completion

31/03/2026

Completed

Project Details

Project Code618072
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateNagaland
Data Month2026-07

Financial Summary

Original Cost₹297 Cr
Revised Cost₹297 Cr
Expenditure₹155 Cr
Original End Date20/07/2024
Revised Date31/03/2026

Project Intelligence

Project is within original budget of ₹297 Cr — no cost escalation recorded.

Expenditure stands at ₹155 Cr, which is 52.2% of the revised project cost.

Remaining budget: ₹142 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening to Existing single lane /intermediate lane to 2 lane from Km185.00 to Km 220.00 of NH-61 New NH-02 in the state of Nagaland. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹297.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening to Existing single lane /intermediate lane to 2 lane from Km185.00 to K"?
Widening to Existing single lane /intermediate lane to 2 lane from Km185.00 to Km 220.00 of NH-61 New NH-02 in the state of Nagaland. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Nagaland. Original cost: ₹297 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹297 Cr has not been significantly revised. Expenditure: ₹155 Cr (52.2% of cost). Data as of 2026-07.
QWhich ministry is responsible for this project?
Widening to Existing single lane /intermediate lane to 2 lan is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618072. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to Existing single lane /intermediate lane to 2 lan is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.