Roads & HighwaysIPM · Central Project#618029

Widening to 4 lane from Km. 133.00 to 158.04 design Chainage Km. 130.88 to 155.145 Shirur Cross to Gaddankeri of NH-367 in the State of Karnataka on EPC mode. Job No. NH-367-KNT-2021-22-930

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹312 CrUtilization: 81.1%

Original Cost

₹351 Cr

Baseline estimate

On budget

Revised Cost

₹312 Cr

Latest approved cost

Expenditure

₹253 Cr

Spent to date

Utilization

81.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹59 Cr

Budget left

Budget Utilization

81.1%
0%25%50%75%100%

Spent

₹253 Cr

Remaining

₹59 Cr

Total

₹312 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

17/01/2025

Revised Completion

31/03/2027

Completed

Project Details

Project Code618029
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹351 Cr
Revised Cost₹312 Cr
Expenditure₹253 Cr
Original End Date17/01/2025
Revised Date31/03/2027

Project Intelligence

Project is within original budget of ₹351 Cr — no cost escalation recorded.

Expenditure stands at ₹253 Cr, which is 81.1% of the revised project cost.

Remaining budget: ₹59 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening to 4 lane from Km. 133.00 to 158.04 design Chainage Km. 130.88 to 155.145 Shirur Cross to Gaddankeri of NH-367 in the State of Karnataka on EPC mode. Job No. NH-367-KNT-2021-22-930 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹351.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening to 4 lane from Km. 133.00 to 158.04 design Chainage Km. 130.88 to 155.1"?
Widening to 4 lane from Km. 133.00 to 158.04 design Chainage Km. 130.88 to 155.145 Shirur Cross to Gaddankeri of NH-367 in the State of Karnataka on EPC mode. Job No. NH-367-KNT-2021-22-930 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹351 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹351 Cr and has been revised to ₹312 Cr — a cost overrun of -11.1%. Expenditure to date: ₹253 Cr (81.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening to 4 lane from Km. 133.00 to 158.04 design Chainage is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618029. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to 4 lane from Km. 133.00 to 158.04 design Chainage is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.