Widening to 4 lane from Km. 133.00 to 158.04 design Chainage Km. 130.88 to 155.145 Shirur Cross to Gaddankeri of NH-367 in the State of Karnataka on EPC mode. Job No. NH-367-KNT-2021-22-930
Original Cost
₹351 Cr
Baseline estimate
Revised Cost
₹312 Cr
Latest approved cost
Expenditure
₹253 Cr
Spent to date
Utilization
81.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹59 Cr
Budget left
Budget Utilization
81.1%Spent
₹253 Cr
Remaining
₹59 Cr
Total
₹312 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
17/01/2025
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹351 Cr — no cost escalation recorded.
Expenditure stands at ₹253 Cr, which is 81.1% of the revised project cost.
Remaining budget: ₹59 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening to 4 lane from Km. 133.00 to 158.04 design Chainage Km. 130.88 to 155.145 Shirur Cross to Gaddankeri of NH-367 in the State of Karnataka on EPC mode. Job No. NH-367-KNT-2021-22-930 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹351.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening to 4 lane from Km. 133.00 to 158.04 design Chainage Km. 130.88 to 155.1"?
- Widening to 4 lane from Km. 133.00 to 158.04 design Chainage Km. 130.88 to 155.145 Shirur Cross to Gaddankeri of NH-367 in the State of Karnataka on EPC mode. Job No. NH-367-KNT-2021-22-930 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹351 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹351 Cr and has been revised to ₹312 Cr — a cost overrun of -11.1%. Expenditure to date: ₹253 Cr (81.1% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening to 4 lane from Km. 133.00 to 158.04 design Chainage is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618029. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to 4 lane from Km. 133.00 to 158.04 design Chainage is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.