Original Cost
₹351 Cr
Baseline estimate
Revised Cost
₹312 Cr
Latest approved cost
Expenditure
₹191 Cr
Spent to date
Utilization
61.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹121 Cr
Budget left
Spent
₹191 Cr
Remaining
₹121 Cr
Total
₹312 Cr
Project Approved
Construction / Implementation
Original End Date
17/01/2025
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹351 Cr — no cost escalation recorded.
Expenditure stands at ₹191 Cr, which is 61.3% of the revised project cost.
Remaining budget: ₹121 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.