Widening to 4 lane from km. 108.50 to km 139.00 of NH-135A Pkg-II Jaunpur Akbarpur section on Hybrid Annuity Mode in the state of Uttar Pradesh
Original Cost
₹1512 Cr
Baseline estimate
Revised Cost
₹1512 Cr
Latest approved cost
Expenditure
₹398 Cr
Spent to date
Utilization
26.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1114 Cr
Budget left
Budget Utilization
26.3%Spent
₹398 Cr
Remaining
₹1114 Cr
Total
₹1512 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
29/03/2027
Revised Completion
29/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1512 Cr — no cost escalation recorded.
Expenditure stands at ₹398 Cr, which is 26.3% of the revised project cost.
Remaining budget: ₹1114 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening to 4 lane from km. 108.50 to km 139.00 of NH-135A Pkg-II Jaunpur Akbarpur section on Hybrid Annuity Mode in the state of Uttar Pradesh is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1512.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening to 4 lane from km. 108.50 to km 139.00 of NH-135A Pkg-II Jaunpur Akbar"?
- Widening to 4 lane from km. 108.50 to km 139.00 of NH-135A Pkg-II Jaunpur Akbarpur section on Hybrid Annuity Mode in the state of Uttar Pradesh is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹1512 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹1512 Cr has not been significantly revised. Expenditure: ₹398 Cr (26.3% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening to 4 lane from km. 108.50 to km 139.00 of NH-135A P is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618249. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to 4 lane from km. 108.50 to km 139.00 of NH-135A P is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.