Widening to 2-Lane with Paved Shoulders from Km 116.800 to 149.070Design Changes on Hosadurga - Holalkere Section of NH-173 in the State of Karnataka on EPC mode under Annual Plan 2021-22 Job no. NH-173-KNT-2021-22-946
Original Cost
₹170 Cr
Baseline estimate
Revised Cost
₹147 Cr
Latest approved cost
Expenditure
₹111 Cr
Spent to date
Utilization
75.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹36 Cr
Budget left
Budget Utilization
75.5%Spent
₹111 Cr
Remaining
₹36 Cr
Total
₹147 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
24/02/2024
Revised Completion
30/06/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹170 Cr — no cost escalation recorded.
Expenditure stands at ₹111 Cr, which is 75.5% of the revised project cost.
Remaining budget: ₹36 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening to 2-Lane with Paved Shoulders from Km 116.800 to 149.070Design Changes on Hosadurga - Holalkere Section of NH-173 in the State of Karnataka on EPC mode under Annual Plan 2021-22 Job no. NH-173-KNT-2021-22-946 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹170.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening to 2-Lane with Paved Shoulders from Km 116.800 to 149.070Design Changes"?
- Widening to 2-Lane with Paved Shoulders from Km 116.800 to 149.070Design Changes on Hosadurga - Holalkere Section of NH-173 in the State of Karnataka on EPC mode under Annual Plan 2021-22 Job no. NH-173-KNT-2021-22-946 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹170 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹170 Cr and has been revised to ₹147 Cr — a cost overrun of -13.3%. Expenditure to date: ₹111 Cr (75.5% of revised cost). Data as of 2026-07.
- QWhich ministry is responsible for this project?
- Widening to 2-Lane with Paved Shoulders from Km 116.800 to 1 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618000. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to 2-Lane with Paved Shoulders from Km 116.800 to 1 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.