Widening, Reconstruction & Up-gradation to 2 lane with Paved Shoulder/Four Lane configuration for the work of Sautada to Shirapur Section of NH-561 from Design km 86300 to km 125589 in the state of Maharashtra on EPC mode. Design length 39.289 km

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹350 CrUtilization: 22.2%

Original Cost

₹350 Cr

Baseline estimate

On budget

Revised Cost

₹350 Cr

Latest approved cost

Expenditure

₹78 Cr

Spent to date

Utilization

22.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹272 Cr

Budget left

Budget Utilization

22.2%
0%25%50%75%100%

Spent

₹78 Cr

Remaining

₹272 Cr

Total

₹350 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

04/11/2026

Revised Completion

04/11/2026

Completed

Project Details

Project Code618138
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹350 Cr
Revised Cost₹350 Cr
Expenditure₹78 Cr
Original End Date04/11/2026
Revised Date04/11/2026

Project Intelligence

Project is within original budget of ₹350 Cr — no cost escalation recorded.

Expenditure stands at ₹78 Cr, which is 22.2% of the revised project cost.

Remaining budget: ₹272 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening, Reconstruction & Up-gradation to 2 lane with Paved Shoulder/Four Lane configuration for the work of Sautada to Shirapur Section of NH-561 from Design km 86300 to km 125589 in the state of Maharashtra on EPC mode. Design length 39.289 km is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹350.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening, Reconstruction & Up-gradation to 2 lane with Paved Shoulder/Four Lane "?
Widening, Reconstruction & Up-gradation to 2 lane with Paved Shoulder/Four Lane configuration for the work of Sautada to Shirapur Section of NH-561 from Design km 86300 to km 125589 in the state of Maharashtra on EPC mode. Design length 39.289 km is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹350 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹350 Cr has not been significantly revised. Expenditure: ₹78 Cr (22.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening, Reconstruction & Up-gradation to 2 lane with Paved is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618138. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening, Reconstruction & Up-gradation to 2 lane with Paved is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.