Widening, Reconstruction & Up-gradation to 2 lane with Paved Shoulder/Four Lane configuration for the work of Ahmednagar to Sabalkhed & Ashti to Chinchpur Section of NH-561 from Design km 2915 to km 37728 & Design km 55100 to km 70000 in the State of Maharashtra on EPC mode. Length 49.713 km

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹657 CrUtilization: 58.3%

Original Cost

₹657 Cr

Baseline estimate

On budget

Revised Cost

₹657 Cr

Latest approved cost

Expenditure

₹383 Cr

Spent to date

Utilization

58.3%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹274 Cr

Budget left

Budget Utilization

58.3%
0%25%50%75%100%

Spent

₹383 Cr

Remaining

₹274 Cr

Total

₹657 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/05/2027

Revised Completion

27/05/2027

Completed

Project Details

Project Code618047
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹657 Cr
Revised Cost₹657 Cr
Expenditure₹383 Cr
Original End Date27/05/2027
Revised Date27/05/2027

Project Intelligence

Project is within original budget of ₹657 Cr — no cost escalation recorded.

Expenditure stands at ₹383 Cr, which is 58.3% of the revised project cost.

Remaining budget: ₹274 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening, Reconstruction & Up-gradation to 2 lane with Paved Shoulder/Four Lane configuration for the work of Ahmednagar to Sabalkhed & Ashti to Chinchpur Section of NH-561 from Design km 2915 to km 37728 & Design km 55100 to km 70000 in the State of Maharashtra on EPC mode. Length 49.713 km is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹657.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening, Reconstruction & Up-gradation to 2 lane with Paved Shoulder/Four Lane "?
Widening, Reconstruction & Up-gradation to 2 lane with Paved Shoulder/Four Lane configuration for the work of Ahmednagar to Sabalkhed & Ashti to Chinchpur Section of NH-561 from Design km 2915 to km 37728 & Design km 55100 to km 70000 in the State of Maharashtra on EPC mode. Length 49.713 km is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹657 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹657 Cr has not been significantly revised. Expenditure: ₹383 Cr (58.3% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening, Reconstruction & Up-gradation to 2 lane with Paved is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618047. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening, Reconstruction & Up-gradation to 2 lane with Paved is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.