Ministry of Road Transport & HighwaysNagaland
Revised Cost: ₹252 CrUtilization: 26.0%

Original Cost

₹252 Cr

Baseline estimate

On budget

Revised Cost

₹252 Cr

Latest approved cost

Expenditure

₹65 Cr

Spent to date

Utilization

26.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹187 Cr

Budget left

Budget Utilization

26.0%
0%25%50%75%100%

Spent

₹65 Cr

Remaining

₹187 Cr

Total

₹252 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

17/06/2026

Revised Completion

17/04/2027

Completed

Project Details

Project Code617886
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateNagaland
Data Month2026-08

Financial Summary

Original Cost₹252 Cr
Revised Cost₹252 Cr
Expenditure₹65 Cr
Original End Date17/06/2026
Revised Date17/04/2027

Project Intelligence

Project is within original budget of ₹252 Cr — no cost escalation recorded.

Expenditure stands at ₹65 Cr, which is 26.0% of the revised project cost.

Remaining budget: ₹187 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening of existing Single lane / Intermediate lane road to 2 lane from Km 101 to Km 125 of NH 61 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹252.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening of existing Single lane / Intermediate lane road to 2 lane from Km 101 "?
Widening of existing Single lane / Intermediate lane road to 2 lane from Km 101 to Km 125 of NH 61 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Nagaland. Original cost: ₹252 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹252 Cr has not been significantly revised. Expenditure: ₹65 Cr (26.0% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening of existing Single lane / Intermediate lane road to is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617886. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening of existing Single lane / Intermediate lane road to is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.