Widening / Improvement to 4-Lane with Paved Shoulder configuration of existing single lane road from Kachukhana Harichara Paglagaunj to Dhubri - Phulbari Bridge approach Package-II of Srirampur - Dhubri Section of NH-127B from existing Km 28.050 to Km 55.060 Design Km 27.650 to Km 54.154, Design Length26.504 Km under JICA ODA Loan assistance Phase-V [Srirampur - Dhubri Pkg-2]

Ministry of Road Transport & HighwaysAssam
Revised Cost: ₹909 CrUtilization: 70.2%

Original Cost

₹909 Cr

Baseline estimate

On budget

Revised Cost

₹909 Cr

Latest approved cost

Expenditure

₹639 Cr

Spent to date

Utilization

70.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹271 Cr

Budget left

Budget Utilization

70.2%
0%25%50%75%100%

Spent

₹639 Cr

Remaining

₹271 Cr

Total

₹909 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

01/01/2025

Revised Completion

30/06/2025

Completed

Project Details

Project Code618372
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAssam
Data Month2026-05

Financial Summary

Original Cost₹909 Cr
Revised Cost₹909 Cr
Expenditure₹639 Cr
Original End Date01/01/2025
Revised Date30/06/2025

Project Intelligence

Project is within original budget of ₹909 Cr — no cost escalation recorded.

Expenditure stands at ₹639 Cr, which is 70.2% of the revised project cost.

Remaining budget: ₹271 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening / Improvement to 4-Lane with Paved Shoulder configuration of existing single lane road from Kachukhana Harichara Paglagaunj to Dhubri - Phulbari Bridge approach Package-II of Srirampur - Dhubri Section of NH-127B from existing Km 28.050 to Km 55.060 Design Km 27.650 to Km 54.154, Design Length26.504 Km under JICA ODA Loan assistance Phase-V [Srirampur - Dhubri Pkg-2] is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹909.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening / Improvement to 4-Lane with Paved Shoulder configuration of existing "?
Widening / Improvement to 4-Lane with Paved Shoulder configuration of existing single lane road from Kachukhana Harichara Paglagaunj to Dhubri - Phulbari Bridge approach Package-II of Srirampur - Dhubri Section of NH-127B from existing Km 28.050 to Km 55.060 Design Km 27.650 to Km 54.154, Design Length26.504 Km under JICA ODA Loan assistance Phase-V [Srirampur - Dhubri Pkg-2] is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹909 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹909 Cr has not been significantly revised. Expenditure: ₹639 Cr (70.2% of cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Widening / Improvement to 4-Lane with Paved Shoulder config is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618372. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening / Improvement to 4-Lane with Paved Shoulder config is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.