Roads & HighwaysIPM · Central Project#618383

Widening and up-gradation to 2-lane with paved shoulder configuration and geometric improvements from km 339.00 to km 380.00 Siaha on Aizawl-Tuipang section under JICA ODA Loan assistance Phase-I Package-8

Ministry of Road Transport & HighwaysMizoram
Revised Cost: ₹637 CrUtilization: 86.6%

Original Cost

₹637 Cr

Baseline estimate

On budget

Revised Cost

₹637 Cr

Latest approved cost

Expenditure

₹552 Cr

Spent to date

Utilization

86.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹85 Cr

Budget left

Budget Utilization

86.6%
0%25%50%75%100%

Spent

₹552 Cr

Remaining

₹85 Cr

Total

₹637 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

15/09/2023

Revised Completion

30/06/2026

Completed

Project Details

Project Code618383
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMizoram
Data Month2026-08

Financial Summary

Original Cost₹637 Cr
Revised Cost₹637 Cr
Expenditure₹552 Cr
Original End Date15/09/2023
Revised Date30/06/2026

Project Intelligence

Project is within original budget of ₹637 Cr — no cost escalation recorded.

Expenditure stands at ₹552 Cr, which is 86.6% of the revised project cost.

Remaining budget: ₹85 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening and up-gradation to 2-lane with paved shoulder configuration and geometric improvements from km 339.00 to km 380.00 Siaha on Aizawl-Tuipang section under JICA ODA Loan assistance Phase-I Package-8 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹637.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening and up-gradation to 2-lane with paved shoulder configuration and geomet"?
Widening and up-gradation to 2-lane with paved shoulder configuration and geometric improvements from km 339.00 to km 380.00 Siaha on Aizawl-Tuipang section under JICA ODA Loan assistance Phase-I Package-8 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Mizoram. Original cost: ₹637 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹637 Cr has not been significantly revised. Expenditure: ₹552 Cr (86.6% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening and up-gradation to 2-lane with paved shoulder conf is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618383. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening and up-gradation to 2-lane with paved shoulder conf is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.