Roads & HighwaysIPM · Central Project +23.8% overrun#618382

Widening and up-gradation to 2-lane with paved shoulder configuration and geometric improvements from km 298.00 to km 339.00 on Aizawl-Tuipang section under JICA ODA Loan assistance Phase-I Package-7

Ministry of Road Transport & HighwaysMizoram
Revised Cost: ₹750 CrUtilization: 0.0%Overrun: +₹144 Cr

Original Cost

₹606 Cr

Baseline estimate

+24% overrun

Revised Cost

₹750 Cr

Latest approved cost

Expenditure

₹0 Cr

Spent to date

Utilization

0.0%

Of revised budget

Escalated

Cost Status

+23.8%

+₹144 Cr increase

Remaining

₹750 Cr

Budget left

Budget Utilization

0.0%
0%25%50%75%100%

Spent

₹0 Cr

Remaining

₹750 Cr

Total

₹750 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹606 Cr

Revised Cost

₹750 Cr

Increase

+₹144 Cr

Escalation

+23.8%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

01/04/2024

Revised Completion

31/05/2025

Completed

Project Details

Project Code618382
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMizoram
Data Month2026-05

Financial Summary

Original Cost₹606 Cr
Revised Cost₹750 Cr
Expenditure₹0 Cr
Original End Date01/04/2024
Revised Date31/05/2025

Project Intelligence

Cost has increased by ₹144 Cr (23.8%) from the original estimate of ₹606 Cr.

Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.

Remaining budget: ₹750 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening and up-gradation to 2-lane with paved shoulder configuration and geometric improvements from km 298.00 to km 339.00 on Aizawl-Tuipang section under JICA ODA Loan assistance Phase-I Package-7 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹606.00 Cr, later revised to ₹750.32 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening and up-gradation to 2-lane with paved shoulder configuration and geomet"?
Widening and up-gradation to 2-lane with paved shoulder configuration and geometric improvements from km 298.00 to km 339.00 on Aizawl-Tuipang section under JICA ODA Loan assistance Phase-I Package-7 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Mizoram. Original cost: ₹606 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹606 Cr and has been revised to ₹750 Cr — a cost overrun of +23.8%. Expenditure to date: ₹0 Cr (0.0% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Widening and up-gradation to 2-lane with paved shoulder conf is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618382. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening and up-gradation to 2-lane with paved shoulder conf is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.