Original Cost
₹769 Cr
Baseline estimate
Revised Cost
₹769 Cr
Latest approved cost
Expenditure
₹169 Cr
Spent to date
Utilization
21.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹600 Cr
Budget left
Spent
₹169 Cr
Remaining
₹600 Cr
Total
₹769 Cr
Project Approved
Construction / Implementation
Original End Date
16/06/2023
Revised Completion
15/05/2025
Completed
Project is within original budget of ₹769 Cr — no cost escalation recorded.
Expenditure stands at ₹169 Cr, which is 21.9% of the revised project cost.
Remaining budget: ₹600 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.