Original Cost
₹867 Cr
Baseline estimate
Revised Cost
₹867 Cr
Latest approved cost
Expenditure
₹159 Cr
Spent to date
Utilization
18.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹708 Cr
Budget left
Spent
₹159 Cr
Remaining
₹708 Cr
Total
₹867 Cr
Project Approved
Construction / Implementation
Original End Date
24/04/2023
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹867 Cr — no cost escalation recorded.
Expenditure stands at ₹159 Cr, which is 18.4% of the revised project cost.
Remaining budget: ₹708 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.