Roads & HighwaysIPM · Central Project#618380

Widening and Up-gradation to 2- Lane with Paved Shoulder Configuration and geometric improvement from Km. 125. 000 to Km 166 Package-3 on Aizawl Tuipang Section of NH-54 in the State of Mizoram Package-3

Ministry of Road Transport & HighwaysMizoram
Revised Cost: ₹867 CrUtilization: 60.6%

Original Cost

₹867 Cr

Baseline estimate

On budget

Revised Cost

₹867 Cr

Latest approved cost

Expenditure

₹525 Cr

Spent to date

Utilization

60.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹342 Cr

Budget left

Budget Utilization

60.6%
0%25%50%75%100%

Spent

₹525 Cr

Remaining

₹342 Cr

Total

₹867 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

24/04/2023

Revised Completion

30/06/2026

Completed

Project Details

Project Code618380
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMizoram
Data Month2026-07

Financial Summary

Original Cost₹867 Cr
Revised Cost₹867 Cr
Expenditure₹525 Cr
Original End Date24/04/2023
Revised Date30/06/2026

Project Intelligence

Project is within original budget of ₹867 Cr — no cost escalation recorded.

Expenditure stands at ₹525 Cr, which is 60.6% of the revised project cost.

Remaining budget: ₹342 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening and Up-gradation to 2- Lane with Paved Shoulder Configuration and geometric improvement from Km. 125. 000 to Km 166 Package-3 on Aizawl Tuipang Section of NH-54 in the State of Mizoram Package-3 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹867.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening and Up-gradation to 2- Lane with Paved Shoulder Configuration and geome"?
Widening and Up-gradation to 2- Lane with Paved Shoulder Configuration and geometric improvement from Km. 125. 000 to Km 166 Package-3 on Aizawl Tuipang Section of NH-54 in the State of Mizoram Package-3 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Mizoram. Original cost: ₹867 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹867 Cr has not been significantly revised. Expenditure: ₹525 Cr (60.6% of cost). Data as of 2026-07.
QWhich ministry is responsible for this project?
Widening and Up-gradation to 2- Lane with Paved Shoulder Con is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618380. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening and Up-gradation to 2- Lane with Paved Shoulder Con is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.