Widening and Strengthening/Reconstruction to Two Lane with Paved Shoulder/ Two Lane with paved shoulders with service road from km 0000 to km 42250 excluding design Ch. 03220 to 04200 & 28350 to 29060 of NH-320G in the state of Jharkhand under EPC mode
Original Cost
₹423 Cr
Baseline estimate
Revised Cost
₹423 Cr
Latest approved cost
Expenditure
₹5 Cr
Spent to date
Utilization
1.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹418 Cr
Budget left
Budget Utilization
1.3%Spent
₹5 Cr
Remaining
₹418 Cr
Total
₹423 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
24/08/2025
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹423 Cr — no cost escalation recorded.
Expenditure stands at ₹5 Cr, which is 1.3% of the revised project cost.
Remaining budget: ₹418 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening and Strengthening/Reconstruction to Two Lane with Paved Shoulder/ Two Lane with paved shoulders with service road from km 0000 to km 42250 excluding design Ch. 03220 to 04200 & 28350 to 29060 of NH-320G in the state of Jharkhand under EPC mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹423.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening and Strengthening/Reconstruction to Two Lane with Paved Shoulder/ Two L"?
- Widening and Strengthening/Reconstruction to Two Lane with Paved Shoulder/ Two Lane with paved shoulders with service road from km 0000 to km 42250 excluding design Ch. 03220 to 04200 & 28350 to 29060 of NH-320G in the state of Jharkhand under EPC mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jharkhand. Original cost: ₹423 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹423 Cr has not been significantly revised. Expenditure: ₹5 Cr (1.3% of cost). Data as of 2026-06.
- QWhich ministry is responsible for this project?
- Widening and Strengthening/Reconstruction to Two Lane with P is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618123. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening and Strengthening/Reconstruction to Two Lane with P is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.