Roads & HighwaysIPM · Central Project#618264

Widening and Strengthening to two Lane with Paved Shoulder/Four Lane with paved shoulder configuration from km. 61.500 of NH-727B near Nawalpur km 178.500 of Sonauli Balia Marg, Old SH-01 i.e. end point of Salempur Bypass to km. 106.495 of NH-727B near Sikanderpur under EPC mode

Ministry of Road Transport & HighwaysUttar Pradesh
Revised Cost: ₹2062 CrUtilization: 29.1%

Original Cost

₹2062 Cr

Baseline estimate

On budget

Revised Cost

₹2062 Cr

Latest approved cost

Expenditure

₹600 Cr

Spent to date

Utilization

29.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1462 Cr

Budget left

Budget Utilization

29.1%
0%25%50%75%100%

Spent

₹600 Cr

Remaining

₹1462 Cr

Total

₹2062 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/05/2028

Revised Completion

30/05/2028

Completed

Project Details

Project Code618264
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttar Pradesh
Data Month2026-08

Financial Summary

Original Cost₹2062 Cr
Revised Cost₹2062 Cr
Expenditure₹600 Cr
Original End Date30/05/2028
Revised Date30/05/2028

Project Intelligence

Project is within original budget of ₹2062 Cr — no cost escalation recorded.

Expenditure stands at ₹600 Cr, which is 29.1% of the revised project cost.

Remaining budget: ₹1462 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening and Strengthening to two Lane with Paved Shoulder/Four Lane with paved shoulder configuration from km. 61.500 of NH-727B near Nawalpur km 178.500 of Sonauli Balia Marg, Old SH-01 i.e. end point of Salempur Bypass to km. 106.495 of NH-727B near Sikanderpur under EPC mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2062.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening and Strengthening to two Lane with Paved Shoulder/Four Lane with paved "?
Widening and Strengthening to two Lane with Paved Shoulder/Four Lane with paved shoulder configuration from km. 61.500 of NH-727B near Nawalpur km 178.500 of Sonauli Balia Marg, Old SH-01 i.e. end point of Salempur Bypass to km. 106.495 of NH-727B near Sikanderpur under EPC mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹2062 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹2062 Cr has not been significantly revised. Expenditure: ₹600 Cr (29.1% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening and Strengthening to two Lane with Paved Shoulder/F is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618264. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening and Strengthening to two Lane with Paved Shoulder/F is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.