Widening and strengthening to 4 lane / 2-lane with paved shoulders of Mahabubnagar - Chincholi section from km 60/255 to Km 102/834 of NH-167N in the State of Telangana on EPC mode.
Original Cost
₹631 Cr
Baseline estimate
Revised Cost
₹631 Cr
Latest approved cost
Expenditure
₹219 Cr
Spent to date
Utilization
34.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹412 Cr
Budget left
Budget Utilization
34.8%Spent
₹219 Cr
Remaining
₹412 Cr
Total
₹631 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
08/10/2025
Revised Completion
02/11/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹631 Cr — no cost escalation recorded.
Expenditure stands at ₹219 Cr, which is 34.8% of the revised project cost.
Remaining budget: ₹412 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening and strengthening to 4 lane / 2-lane with paved shoulders of Mahabubnagar - Chincholi section from km 60/255 to Km 102/834 of NH-167N in the State of Telangana on EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹631.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening and strengthening to 4 lane / 2-lane with paved shoulders of Mahabubnag"?
- Widening and strengthening to 4 lane / 2-lane with paved shoulders of Mahabubnagar - Chincholi section from km 60/255 to Km 102/834 of NH-167N in the State of Telangana on EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Telangana. Original cost: ₹631 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹631 Cr has not been significantly revised. Expenditure: ₹219 Cr (34.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening and strengthening to 4 lane / 2-lane with paved sho is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618105. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening and strengthening to 4 lane / 2-lane with paved sho is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.