Roads & HighwaysIPM · Central Project#618201

Widening and strengthening to 2 lane with paved shoulder from existing Ch. Km 56720 to Km 100820 and Design Ch. From Km 62600 to Km 106360 Total Length43.760 Km on SRINAGAR -BARAMULA URINH-01 in the UT of Jammu & Kashmir under project BEACON, Border Roads Organization BRO on EPC mode.

Ministry of Road Transport & HighwaysJammu & Kashmir
Revised Cost: ₹702 CrUtilization: 26.8%

Original Cost

₹702 Cr

Baseline estimate

On budget

Revised Cost

₹702 Cr

Latest approved cost

Expenditure

₹188 Cr

Spent to date

Utilization

26.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹514 Cr

Budget left

Budget Utilization

26.8%
0%25%50%75%100%

Spent

₹188 Cr

Remaining

₹514 Cr

Total

₹702 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

17/11/2026

Revised Completion

30/06/2027

Completed

Project Details

Project Code618201
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJammu & Kashmir
Data Month2026-08

Financial Summary

Original Cost₹702 Cr
Revised Cost₹702 Cr
Expenditure₹188 Cr
Original End Date17/11/2026
Revised Date30/06/2027

Project Intelligence

Project is within original budget of ₹702 Cr — no cost escalation recorded.

Expenditure stands at ₹188 Cr, which is 26.8% of the revised project cost.

Remaining budget: ₹514 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening and strengthening to 2 lane with paved shoulder from existing Ch. Km 56720 to Km 100820 and Design Ch. From Km 62600 to Km 106360 Total Length43.760 Km on SRINAGAR -BARAMULA URINH-01 in the UT of Jammu & Kashmir under project BEACON, Border Roads Organization BRO on EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹702.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening and strengthening to 2 lane with paved shoulder from existing Ch. Km 56"?
Widening and strengthening to 2 lane with paved shoulder from existing Ch. Km 56720 to Km 100820 and Design Ch. From Km 62600 to Km 106360 Total Length43.760 Km on SRINAGAR -BARAMULA URINH-01 in the UT of Jammu & Kashmir under project BEACON, Border Roads Organization BRO on EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jammu & Kashmir. Original cost: ₹702 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹702 Cr has not been significantly revised. Expenditure: ₹188 Cr (26.8% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening and strengthening to 2 lane with paved shoulder fro is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618201. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening and strengthening to 2 lane with paved shoulder fro is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.