Roads & HighwaysIPM · Central Project#618178

Widening and strengthening of Gangakhed to Kingaon section of NH-752K in Km 38/750 to 72/304 Flexible Pavement Length33.554 km to 2-lane configuration on EPC mode in the State of Maharashtra.

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹163 CrUtilization: 3.5%

Original Cost

₹163 Cr

Baseline estimate

On budget

Revised Cost

₹163 Cr

Latest approved cost

Expenditure

₹6 Cr

Spent to date

Utilization

3.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹157 Cr

Budget left

Budget Utilization

3.5%
0%25%50%75%100%

Spent

₹6 Cr

Remaining

₹157 Cr

Total

₹163 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

03/06/2026

Revised Completion

30/10/2026

Completed

Project Details

Project Code618178
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹163 Cr
Revised Cost₹163 Cr
Expenditure₹6 Cr
Original End Date03/06/2026
Revised Date30/10/2026

Project Intelligence

Project is within original budget of ₹163 Cr — no cost escalation recorded.

Expenditure stands at ₹6 Cr, which is 3.5% of the revised project cost.

Remaining budget: ₹157 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening and strengthening of Gangakhed to Kingaon section of NH-752K in Km 38/750 to 72/304 Flexible Pavement Length33.554 km to 2-lane configuration on EPC mode in the State of Maharashtra. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹163.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening and strengthening of Gangakhed to Kingaon section of NH-752K in Km 38/7"?
Widening and strengthening of Gangakhed to Kingaon section of NH-752K in Km 38/750 to 72/304 Flexible Pavement Length33.554 km to 2-lane configuration on EPC mode in the State of Maharashtra. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹163 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹163 Cr has not been significantly revised. Expenditure: ₹6 Cr (3.5% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening and strengthening of Gangakhed to Kingaon section o is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618178. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening and strengthening of Gangakhed to Kingaon section o is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.