Widening and Reconstruction to 4-lane/4-lane with service road including structures from Pokharia More at Km 47.600 Ex. Km 50.230 to Govindpur at km 62.949 Ex. Km 65.325 of Nh-419 in the State of Jharkhand on EPC mode.
Original Cost
₹300 Cr
Baseline estimate
Revised Cost
₹300 Cr
Latest approved cost
Expenditure
₹176 Cr
Spent to date
Utilization
58.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹124 Cr
Budget left
Budget Utilization
58.6%Spent
₹176 Cr
Remaining
₹124 Cr
Total
₹300 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
03/01/2026
Revised Completion
03/01/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹300 Cr — no cost escalation recorded.
Expenditure stands at ₹176 Cr, which is 58.6% of the revised project cost.
Remaining budget: ₹124 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening and Reconstruction to 4-lane/4-lane with service road including structures from Pokharia More at Km 47.600 Ex. Km 50.230 to Govindpur at km 62.949 Ex. Km 65.325 of Nh-419 in the State of Jharkhand on EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹300.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening and Reconstruction to 4-lane/4-lane with service road including structu"?
- Widening and Reconstruction to 4-lane/4-lane with service road including structures from Pokharia More at Km 47.600 Ex. Km 50.230 to Govindpur at km 62.949 Ex. Km 65.325 of Nh-419 in the State of Jharkhand on EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jharkhand. Original cost: ₹300 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹300 Cr has not been significantly revised. Expenditure: ₹176 Cr (58.6% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening and Reconstruction to 4-lane/4-lane with service ro is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618242. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening and Reconstruction to 4-lane/4-lane with service ro is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.