Original Cost
₹4052 Cr
Baseline estimate
Revised Cost
₹4316 Cr
Latest approved cost
Expenditure
₹906 Cr
Spent to date
Utilization
21.0%
Of revised budget
Cost Status
+6.5%
+₹264 Cr increase
Remaining
₹3410 Cr
Budget left
Spent
₹906 Cr
Remaining
₹3410 Cr
Total
₹4316 Cr
Original Cost
₹4052 Cr
Revised Cost
₹4316 Cr
Increase
+₹264 Cr
Escalation
+6.5%
Project Approved
Construction / Implementation
Original End Date
31/10/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹264 Cr (6.5%) from the original estimate of ₹4052 Cr.
Expenditure stands at ₹906 Cr, which is 21.0% of the revised project cost.
Remaining budget: ₹3410 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.