Original Cost
₹2611 Cr
Baseline estimate
Revised Cost
₹2918 Cr
Latest approved cost
Expenditure
₹622 Cr
Spent to date
Utilization
21.3%
Of revised budget
Cost Status
+11.8%
+₹307 Cr increase
Remaining
₹2297 Cr
Budget left
Spent
₹622 Cr
Remaining
₹2297 Cr
Total
₹2918 Cr
Original Cost
₹2611 Cr
Revised Cost
₹2918 Cr
Increase
+₹307 Cr
Escalation
+11.8%
Project Approved
Construction / Implementation
Original End Date
11/05/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹307 Cr (11.8%) from the original estimate of ₹2611 Cr.
Expenditure stands at ₹622 Cr, which is 21.3% of the revised project cost.
Remaining budget: ₹2297 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.