Original Cost
₹1711 Cr
Baseline estimate
Revised Cost
₹2389 Cr
Latest approved cost
Expenditure
₹979 Cr
Spent to date
Utilization
41.0%
Of revised budget
Cost Status
+39.6%
+₹678 Cr increase
Remaining
₹1409 Cr
Budget left
Spent
₹979 Cr
Remaining
₹1409 Cr
Total
₹2389 Cr
Original Cost
₹1711 Cr
Revised Cost
₹2389 Cr
Increase
+₹678 Cr
Escalation
+39.6%
Project Approved
Construction / Implementation
Original End Date
22/03/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹678 Cr (39.6%) from the original estimate of ₹1711 Cr.
Expenditure stands at ₹979 Cr, which is 41.0% of the revised project cost.
Remaining budget: ₹1409 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.