Vadodara Mumbai Expressway Kim to Ankleshwar Phase IA - Pkg V
Original Cost
₹1325 Cr
Baseline estimate
Revised Cost
₹2807 Cr
Latest approved cost
Expenditure
₹1547 Cr
Spent to date
Utilization
55.1%
Of revised budget
Cost Status
+111.9%
+₹1482 Cr increase
Remaining
₹1260 Cr
Budget left
Budget Utilization
55.1%Spent
₹1547 Cr
Remaining
₹1260 Cr
Total
₹2807 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1325 Cr
Revised Cost
₹2807 Cr
Increase
+₹1482 Cr
Escalation
+111.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/10/2021
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹1482 Cr (111.9%) from the original estimate of ₹1325 Cr.
Expenditure stands at ₹1547 Cr, which is 55.1% of the revised project cost.
Remaining budget: ₹1260 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Vadodara Mumbai Expressway Kim to Ankleshwar Phase IA - Pkg V is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1325.00 Cr, later revised to ₹2807.48 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Vadodara Mumbai Expressway Kim to Ankleshwar Phase IA - Pkg V"?
- Vadodara Mumbai Expressway Kim to Ankleshwar Phase IA - Pkg V is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹1325 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1325 Cr and has been revised to ₹2807 Cr — a cost overrun of +111.9%. Expenditure to date: ₹1547 Cr (55.1% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Vadodara Mumbai Expressway Kim to Ankleshwar Phase IA - Pkg is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618463. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Vadodara Mumbai Expressway Kim to Ankleshwar Phase IA - Pkg is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.