Original Cost
₹1325 Cr
Baseline estimate
Revised Cost
₹2807 Cr
Latest approved cost
Expenditure
₹1276 Cr
Spent to date
Utilization
45.4%
Of revised budget
Cost Status
+111.9%
+₹1482 Cr increase
Remaining
₹1532 Cr
Budget left
Spent
₹1276 Cr
Remaining
₹1532 Cr
Total
₹2807 Cr
Original Cost
₹1325 Cr
Revised Cost
₹2807 Cr
Increase
+₹1482 Cr
Escalation
+111.9%
Project Approved
Construction / Implementation
Original End Date
31/10/2021
Revised Completion
31/07/2026
Completed
Cost has increased by ₹1482 Cr (111.9%) from the original estimate of ₹1325 Cr.
Expenditure stands at ₹1276 Cr, which is 45.4% of the revised project cost.
Remaining budget: ₹1532 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.