Original Cost
₹150 Cr
Baseline estimate
Revised Cost
₹150 Cr
Latest approved cost
Expenditure
₹12 Cr
Spent to date
Utilization
8.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹138 Cr
Budget left
Spent
₹12 Cr
Remaining
₹138 Cr
Total
₹150 Cr
Project Approved
Construction / Implementation
Original End Date
01/09/2024
Revised Completion
30/09/2025
Completed
Project is within original budget of ₹150 Cr — no cost escalation recorded.
Expenditure stands at ₹12 Cr, which is 8.1% of the revised project cost.
Remaining budget: ₹138 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.