Upgradation to 4L PS from Bhimasar, Junction of NH-41 to Anjar- Bhuj upto Airport Junction from Km 0.000 to Km 65.478 of NH-341
Original Cost
₹1373 Cr
Baseline estimate
Revised Cost
₹1687 Cr
Latest approved cost
Expenditure
₹838 Cr
Spent to date
Utilization
49.7%
Of revised budget
Cost Status
+22.9%
+₹314 Cr increase
Remaining
₹849 Cr
Budget left
Budget Utilization
49.7%Spent
₹838 Cr
Remaining
₹849 Cr
Total
₹1687 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1373 Cr
Revised Cost
₹1687 Cr
Increase
+₹314 Cr
Escalation
+22.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
29/06/2025
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹314 Cr (22.9%) from the original estimate of ₹1373 Cr.
Expenditure stands at ₹838 Cr, which is 49.7% of the revised project cost.
Remaining budget: ₹849 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Upgradation to 4L PS from Bhimasar, Junction of NH-41 to Anjar- Bhuj upto Airport Junction from Km 0.000 to Km 65.478 of NH-341 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1373.00 Cr, later revised to ₹1687.25 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Upgradation to 4L PS from Bhimasar, Junction of NH-41 to Anjar- Bhuj upto Airpo"?
- Upgradation to 4L PS from Bhimasar, Junction of NH-41 to Anjar- Bhuj upto Airport Junction from Km 0.000 to Km 65.478 of NH-341 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹1373 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1373 Cr and has been revised to ₹1687 Cr — a cost overrun of +22.9%. Expenditure to date: ₹838 Cr (49.7% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Upgradation to 4L PS from Bhimasar, Junction of NH-41 to An is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618787. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Upgradation to 4L PS from Bhimasar, Junction of NH-41 to An is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.