Original Cost
₹1373 Cr
Baseline estimate
Revised Cost
₹1687 Cr
Latest approved cost
Expenditure
₹838 Cr
Spent to date
Utilization
49.6%
Of revised budget
Cost Status
+22.9%
+₹314 Cr increase
Remaining
₹850 Cr
Budget left
Spent
₹838 Cr
Remaining
₹850 Cr
Total
₹1687 Cr
Original Cost
₹1373 Cr
Revised Cost
₹1687 Cr
Increase
+₹314 Cr
Escalation
+22.9%
Project Approved
Construction / Implementation
Original End Date
29/06/2025
Revised Completion
30/09/2026
Completed
Cost has increased by ₹314 Cr (22.9%) from the original estimate of ₹1373 Cr.
Expenditure stands at ₹838 Cr, which is 49.6% of the revised project cost.
Remaining budget: ₹850 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.